BLD-Final | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
DOC - Permit Finaled | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PART |
Mike Jordan
|
|
|
All other inspections have been performed. Owner posted landscape bond as per zoning temporary sign off requirements. Phone #: ###-#### Inspection requested via web by Antonio Carone. Ok for temp. occ. Will be ok for perm occ. once zoning and public works signs perm.
|
BLD-Final | 6/6/2016 | 6/6/2016 | 6/7/2016 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
FIRE-Final Inspection | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide address numbers facing the street, as discussed, prior to a building inspection.
|
BLD-Conference | 4/29/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Mike Jordan
|
|
|
I will not be onsite this morning. I have dry wallers waiting to hang. Please send me a text or voice mail with the status. Thank you Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Final | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Framing/Rough-in | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Wall Bracing | 3/31/2016 | 3/31/2016 | 3/31/2016 | P | PASS |
Mike Jordan
|
|
|
Sheer inspection Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Framing/Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Mike Jordan
|
|
|
Roof nail inspection request for approval to cover. Phone #: ###-#### Inspection requested via web by Antonio Carone
|
BLD-Footing | 1/27/2016 | 1/28/2016 | 1/28/2016 | P | PASS |
Jim Sly
|
|
|
Have concrete scheduled for 1:00pm. We would like to be as close to 12:00pm as possible with the inspection for footings. Phone #: ###-#### Inspection requested via web by Antonio Carone
No special insp req. besides soil. Footing OK.
|
BLD-Conference | 1/27/2016 | 1/27/2016 | 1/27/2016 | A | DEFR |
Mike Jordan
|
|
|
Per structural engineer for the project David Sansotta, no special inspections required for the 1500 psf minimum bearing pressures soil however he requested that the city inspector verify the conditions are acceptable. Footings are excavated and the soil appears to meet or exceed the allowable requirements. Request a conference to confer with inspector. Call Antonio Carone with questions. Phone #: ###-#### Inspection requested via web by Antonio Carone. No geo-tech report for project. Project site has had 2ft. to 3ft. of uncontrolled fill from previous construction to the south. Also noted construction debries within the building pad site and excavated footings. Noted to contractor that a sub grade inspection would be required by a geo-tech engineer.
|