Information based on query as of Thursday, June 27, 2024.
Permit Information
Permit NumberBLD15-03537
StatusFinaled
Name JP2 CONSTRUCTION LLC
Site Address 1501 W JEFFERSON ST
Project NameThe Sturiale Place
Customer Number 
ePlanReviewYes
Description
(THE STURIALE PLACE - **Foundation Only**)(**GREEN TAG PRIORITY REVIEW) Application for foundation and site improvements only. A SEPARATE PERMIT WILL BE REQUIRED FOR THE HOUSE MOVE AND INTERIOR MODIFICATIONS TO THE STRUCTURE TO CONVERT IT TO A COMMERCIAL USE. Relocation of the historic M.B. Zimmer/Mary Wood Queen Anne Cottage from it's current Central Addition location (412 5th Street) to the proposed site at the corner of 15th and Jefferson. Also proposed will be a partial basement of approximately 1,218 square feet under a part of the existing and entire new addition which is an approximately 660 square foot addition to the rear of the building. Site improvements would include extensive landscaping, parking off the rear alley and on-site drainage. The current use will be changed from single-family residential to a commercial retail/coffee shop use with full mechanical, electrical, plumbing and A.D.A. upgrades.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/17/20163/21/20163/21/2016ADONE
DetailsTony Young
This is the final inspection for the Foundation Permit Only as that portion of the work has been completed. Balance of project will be done under Permit #BLD15-04326 Thanks! Phone #: ###-#### Inspection requested via web by Joseph Perkins
DOC - Permit Finaled3/21/20163/21/20163/21/2016PPASS
DetailsTony Young
foundation ok to final
BLD-Final3/16/20163/18/20163/17/2016ACANC
DetailsTony Young
This is the final inspection for the Foundation Permit Only as that portion of the work has been completed. Balance of project will be done under Permit #BLD15-04326 Phone #: ###-#### >> Inspection requested via web by Joseph Perkins Inspection cancelled from web by: Joseph Perkins
BLD-Framing/Rough-in2/11/20162/12/20162/12/2016APART
DetailsTony Young
Framing for basement/ structural portion only. Balance of framing to be included at later date. Phone #: ###-#### Inspection requested via web by Joseph Perkins,,, ok to deck joists and basement structure is ok so far..
BLD-Concrete1/29/20162/1/20162/1/2016APART
DetailsTony Young
Remainder of Basement Floor Slab and Thickened Footings for Columns, Infill of blockouts in stem wall from structural beams. Pour Scheduled for 10:30. Thank You Phone #: ###-#### Inspection requested via web by Joseph Perkins
BLD-Concrete1/7/20161/8/20161/8/2016APASS
DetailsTony Young
Stem Walls for Crawl Space area of basement Phone #: ###-#### Inspection requested via web by Joseph Perkins
BLD-Footing1/4/20161/6/20161/6/2016APASS
DetailsMike Jordan
Footings for Crawl Space portion of home and addition Phone #: ###-#### Inspection requested via web by Joseph Perkins
BLD-Footing12/11/201512/14/201512/14/2015APART
DetailsTony Young
Concrete Stemwalls for Full Basement Area. Late AM inspection preferred if possible. Phone #: ###-#### Inspection requested via web by Joseph Perkins,,, work in progress,, ok
BLD-Footing12/3/201512/4/201512/4/2015APART
DetailsDave Hannah
Footings and Rebar Phone #: ###-#### Inspection requested via web by Joseph Perkins basement ftgs ok to pour