BLD-Final | 3/17/2016 | 3/21/2016 | 3/21/2016 | A | DONE |
Tony Young
|
|
|
This is the final inspection for the Foundation Permit Only as that portion of the work has been completed. Balance of project will be done under Permit #BLD15-04326 Thanks! Phone #: ###-#### Inspection requested via web by Joseph Perkins
|
DOC - Permit Finaled | 3/21/2016 | 3/21/2016 | 3/21/2016 | P | PASS |
Tony Young
|
|
|
foundation ok to final
|
BLD-Final | 3/16/2016 | 3/18/2016 | 3/17/2016 | A | CANC |
Tony Young
|
|
|
This is the final inspection for the Foundation Permit Only as that portion of the work has been completed. Balance of project will be done under Permit #BLD15-04326 Phone #: ###-#### >> Inspection requested via web by Joseph Perkins Inspection cancelled from web by: Joseph Perkins
|
BLD-Framing/Rough-in | 2/11/2016 | 2/12/2016 | 2/12/2016 | A | PART |
Tony Young
|
|
|
Framing for basement/ structural portion only. Balance of framing to be included at later date. Phone #: ###-#### Inspection requested via web by Joseph Perkins,,, ok to deck joists and basement structure is ok so far..
|
BLD-Concrete | 1/29/2016 | 2/1/2016 | 2/1/2016 | A | PART |
Tony Young
|
|
|
Remainder of Basement Floor Slab and Thickened Footings for Columns, Infill of blockouts in stem wall from structural beams. Pour Scheduled for 10:30. Thank You Phone #: ###-#### Inspection requested via web by Joseph Perkins
|
BLD-Concrete | 1/7/2016 | 1/8/2016 | 1/8/2016 | A | PASS |
Tony Young
|
|
|
Stem Walls for Crawl Space area of basement Phone #: ###-#### Inspection requested via web by Joseph Perkins
|
BLD-Footing | 1/4/2016 | 1/6/2016 | 1/6/2016 | A | PASS |
Mike Jordan
|
|
|
Footings for Crawl Space portion of home and addition Phone #: ###-#### Inspection requested via web by Joseph Perkins
|
BLD-Footing | 12/11/2015 | 12/14/2015 | 12/14/2015 | A | PART |
Tony Young
|
|
|
Concrete Stemwalls for Full Basement Area. Late AM inspection preferred if possible. Phone #: ###-#### Inspection requested via web by Joseph Perkins,,, work in progress,, ok
|
BLD-Footing | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | PART |
Dave Hannah
|
|
|
Footings and Rebar Phone #: ###-#### Inspection requested via web by Joseph Perkins basement ftgs ok to pour
|