Permit Information
Permit NumberBLD15-04136
StatusFinaled
Name CSDI CONSTRUCTION INC
Site Address 1015 N 8TH ST
Project NameChildren's School of Boise
Customer Number 
ePlanReviewYes
Description
(CHILDREN’S SCHOOL OF BOISE - Addition) Permit is to construct a new 2,043 (1,435 square foot basement) square foot addition to an existing 4,870 square feet (1,130 square foot basement) creating a new 7,905 square foot school building (2,565 square foot basement). Approval contingent upon adhering to the approved plans on file and attached engineering. This building is not Fire sprinklered (each class has exterior exit).This building is utilizing the lighting as their additional energy efficiency package. Work to include: construct new basement, construct wood framed exterior walls / truss system, [construct new interior nonbearing walls to create two new classrooms, office, and restroom], new plumbing, new mechanical, new electrical and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/4/20168/4/20168/4/2016PDONE
DetailsTony Young
as per phone call with Tony Young all requirments were met
BLD-Final7/19/20167/21/20167/21/2016PPART
DetailsJim Storey
Mark Phone #: ###-####
Informed Mark, as of 10:44am 7/19, that C & S Excavation hasn't paid for their permit or had inspections need health dept insp/
FIRE-Final Inspection7/20/20167/21/20167/21/2016APASS
DetailsJim Page
No fire sprinklers, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIRE-Final Inspection7/19/20167/20/20167/20/2016ACANC
DetailsJim Page
Inspection request will need to be rescheduled to coincide with FIR permit final.
BLD-Conference7/11/20167/11/20167/11/2016PPEND
DetailsTony Young
Mark Phone #: ###-####,, walk through only,, need trades,, historical,, guard rails per code,, handrails per code,, etc.
BLD-Energy code compliance6/1/20166/2/20166/2/2016APASS
DetailsMike Jordan
Mark Phone #: ###-####. Exterior walls ok. Needs to complete airseal pak and fire block interior walls.
BLD-Energy code compliance5/27/20165/31/20165/31/2016PNR
DetailsDave Hannah
Mark Phone #: ###-####
BLD-Framing/Rough-in5/27/20165/27/20165/27/2016PPART
DetailsTony Young
Mark Phone #: ###-####,, walls ok to insulate main level
BLD-Conference5/20/20165/20/20165/20/2016PPASS
DetailsTony Young
Mark Phone #: ###-####,, walk through on frame
BLD-Framing/Rough-in5/19/20165/20/20165/20/2016ANR
DetailsTony Young
Mark Phone #: ###-####
BLD-Framing/Rough-in5/18/20165/18/20165/18/2016PPART
DetailsTony Young
partial frame on roof-Mark Phone #: ###-####,, ROOF NAILING OK
BLD-Foundation3/29/20163/30/20163/30/2016APART
DetailsTony Young
rebar; Mark Phone #: ###-####,, ok pending special inspection
BLD-Footing3/28/20163/28/20163/28/2016PCANC
DetailsTony Young
Late if possible // Mark Phone #: ###-####
BLD-Foundation3/28/20163/28/20163/28/2016PCANC
DetailsTony Young
Late if possible......Rebar // Mark Phone #: ###-####