BLD-Final | 3/28/2016 | 3/29/2016 | 3/29/2016 | P | PASS |
Phil Shearer
|
|
|
Miles Phone #: ###-####
|
FIRE-Final Inspection | 3/28/2016 | 3/29/2016 | 3/29/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. Wall has been completed.
|
FIRE-Final Inspection | 3/28/2016 | 3/29/2016 | 3/29/2016 | P | CANC |
Troy Cobbley
|
|
|
Miles Phone #: ###-####
|
BLD-Final | 3/9/2016 | 3/9/2016 | 3/9/2016 | A | PART |
Phil Shearer
|
|
|
Spoke with Phil and he gave the ok for a partial final
|
BLD-Conference | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | PART |
Phil Shearer
|
|
|
Troy is doing the fire final this morning. Phone #: ###-#### Inspection requested via web by Miles Hash. OK for Temp
|
FIRE-Final Inspection | 2/26/2016 | 2/29/2016 | 2/29/2016 | P | PART |
Troy Cobbley
|
|
|
A temporay occupancy is being given with Scott's permission. As per the fire code review comments, a 1 hour wall needs to be provided. It does not appear that "house keeping" should be an issue due to construction type and size of the booth. Per ESI superintendant the wall will be installed with-in the two week time period for a temporary occupancy. A follow up inspection for myself has been scheduled.
|
FIRE-Conference | 2/25/2016 | 2/25/2016 | 2/26/2016 | P | DONE |
Troy Cobbley
|
|
|
Went over life safety requirements. Need thumbturn off of front door and add emergency lighting in the front office.
|
BLD-Ceiling Grid Inspection | 2/3/2016 | 2/4/2016 | 2/4/2016 | A | PASS |
Phil Shearer
|
|
|
please call before arriving, working 2 jobs thanks. Phone #: ###-#### Inspection requested via web by Miles Hash
|
BLD-Framing/Rough-in | 1/13/2016 | 1/14/2016 | 1/14/2016 | A | PASS |
Dave Hannah
|
|
|
completed framing, can complete framing inspections, thanks Phone #: ###-#### Inspection requested via web by Miles Hash
|
BLD-Framing/Rough-in | 1/12/2016 | 1/12/2016 | 1/12/2016 | P | PASS |
Phil Shearer
|
|
|
inspect demising wall so sheetrock and rough-in can happen. thanks Miles Phone #: ###-#### Inspection requested via web by Miles Hash
|