Information based on query as of Wednesday, June 19, 2024.
Permit Information
Permit NumberBLD15-04260
StatusFinaled
Name ESI
Site Address 8300 W OVERLAND RD
Project NameWalmart Growler Station
Customer Number 
ePlanReviewYes
Description
** (GROWLER STATION - WALMART) ** Permit is to remodel an existing 551 sq. ft. vacant tenant space within a 230,935 sq. ft. retail store. Work to include: removal of select wall for new opening, construction of select interior nonbearing walls to create a storage area, a sales area and an equipment alcove, new millwork, adding new and relocating existing light fixtures, relocate electrical panel, new sinks, water heater and plumbing work, electrical work, relocate mechanical ductwork and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/1/20163/2/20163/2/2016APASS
DetailsMike Jordan
The Plumbing Final is scheduled for early AM (8:30am) per coordination between the plumber and the City Plumbing Inspector. If at all possible, we would like the Building Final Inspection between 10am and 12pm. Thanks. Phone #: ###-#### Inspection requested via web by Ted Owens. Ok for perm occ. Contractor has chosen to blank key lock on security grill from both sides.
BLD-Final2/26/20162/26/20162/26/2016PFAIL
DetailsMike Jordan
Plumbing to be done pm today as well-Improvements complete. Requesting final inspections as deemed necessary by the City of Boise. Phone #: ###-#### Inspection requested via web by Ted Owens. Provide a means to open the security grill from the inside with out the use of key or special knowledge. Plumbing final has also failed.
BLD-Ceiling Grid Inspection2/26/20162/26/20162/26/2016PDONE
DetailsMike Jordan
Plumbing to be done pm today as well-Improvements complete. Requesting final inspections as deemed necessary by the City of Boise for the Certificate of Occupancy. The ceiling tiles were replaced with new ceiling tile and only minor corrections were necessary to replace existing bent or stained T-bars. Phone #: ###-#### Inspection requested via web by Ted Owens. grid is existing.
FIRE-Final Inspection2/26/20162/26/20162/26/2016APASS
DetailsTroy Cobbley
Life safety passed
BLD-Framing/Rough-in2/10/20162/10/20162/10/2016PPASS
DetailsMike Jordan
The framing is complete, and the in-wall electrical has passed. The in-wall plumbing is complete and should be on schedule for inspection today. I just want to make certain that is missed for inspection requirement and that the framing itself is inspected even though it is a smaller project. The door has a simple combination lock for public safety. The combination is 2508. The reviewed/accepted plans are inside the permit work area. I can meet the inspector on site if needed.

Thanks,

Ted Owens- ESI Proj Supt Phone #: ###-#### Inspection requested via web by Ted Owens. INterior steel stud framed walls ok.