Permit Information
Permit NumberBLD15-04468
StatusFinaled
Name ESI
Site Address 850 W FRONT ST
Project NameBoise Centre Walkway
Customer Number 
ePlanReviewYes
Description
**Project Management-Ron Hill** (BOISE CENTRE LOBBY EXPANSION, TERRACE, PEDESTRIAN WALKWAY, AND CONCOURSE) (DRH15-00462) (1-13-17 PLAN MODIFICATION TO INCORPORATE INTO THE APPROVED DRAWINGS VARIOUS STRUCTURAL SKETCHES THAT HAVE BEEN ISSUED DURING CONSTRUCTION AS A RESULT OF REQUESTS FOR INFORMATION [RFI].) Fire sprinkler systems used for high-rise and for occupancy. To expand a portion of the existing Boise Centre Convention building by constructing a 2nd story to create a vertical circulation route to a new elevated pedestrian walkway and enclosed elevated concourse that will connect the Boise Centre Convention building to the City Center Plaza building (3,603 square feet total). The floor of the new elevated circulation route will be located about 24 feet above grade, at the perimeter of The Grove. The concourse will be part of the Century Link Arena building. A terrace will also be constructed at the Boise Centre Convention building adjacent to The Grove. Work is to include an elevator, an escalator, two egress stairways, exterior walls, interior doors, and finishes. Structural work includes micro piles, helical piers, concrete footings, concrete foundations, steel columns, steel beams, a moment frame, a horizontal truss, steel pan deck and concrete floors, masonry walls, etc. Special Inspection is required for fabricators, steel, welding, concrete, masonry, soils, cast-in-place deep foundations (micro piles), helical piers, epoxy anchors, other post installed concrete anchors, seismic resistance, bolting, and spray-applied fire resistant materials. Post tensioned concrete slabs are required to be scanned to locate rebar, including tendons, before any holes are drilled. No rebar, including tendons, are allowed to be cut. Structural observations by the Structural Engineer of Record will be provided as noted on the drawings. The stairway design is a deferred submittal item. Property easements are required to allow construction within CCDC property. The work is required to comply with the approved drawings, with the plan review report, with the structural design, with the approved code alternates, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/8/201711/8/201711/8/2017PPASS
DetailsDave Hannah
Corey Phone #: ###-####
FIRE-Final Inspection11/8/201711/8/201711/8/2017APASS
DetailsJim Page
Fire alarm panel integration complete for link, final life fire safety inspection passed/complete.
BLD-Aging Inspection9/25/20179/25/201710/2/2017 PEND
DetailsDave Hannah
BLD-Final7/6/20177/10/20177/11/2017PPART
DetailsDave Hannah
Adam Phone #: ###-#### ok for perm after all other work and trades are finaled
FIRE-Final Inspection7/6/20177/10/20177/10/2017APART
DetailsJim Page
Life fire safety inspection complete with exception to the communication between fire panels with the link, TCO extension approved for 30 days in regards to life fire safey per conversation with Scott Arellano.
BLD-Aging Inspection6/19/20176/19/20176/20/2017 PEND
DetailsDave Hannah
BLD-Final3/30/20173/30/20173/31/2017APART
DetailsDave Hannah
Final walk am attempt. Call Adam. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for T.C.O.
FIRE-Final Inspection3/29/20173/30/20173/30/2017APART
DetailsJim Page
Partial life fire safety inspection complete for TCO requested area's (GBAD link, Century Link, Boise Center, escalator lobby levels 1 and 2, elevated concourse between Boise Center and west stairwell) Fire sprinklers are complete for TCO area, fire alarms are complete for TCO area, fire extinguishers are in place with current inspection tags.
BLD-Final3/27/20173/29/20173/29/2017PCANC
DetailsDave Hannah
PM walk to review status. Call Adam before heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
FIRE-Final Inspection3/27/20173/29/20173/29/2017PCANC
DetailsJim Page
Scheduled for 8AM on 30MAR2017
BLD-Conference3/27/20173/28/20173/29/2017PPASS
DetailsDave Hannah
PM walk to review status. Call Adam before heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Conference3/27/20173/27/20173/27/2017PCANC
DetailsMike Jordan
PM walk to review status. Call Adam before heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Conference3/20/20173/24/20173/27/2017PPART
DetailsDave Hannah
Conference walk to review any items. Call in advance. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson ext fire walls above fir doors
FIRE-Conference3/23/20173/23/20173/23/2017PDONE
DetailsJim Page
Fire conference complete
FIRE-Conference3/22/20173/23/20173/23/2017ACANC
DetailsJim Page
BLD-Conference3/20/20173/22/20173/23/2017PPASS
DetailsDave Hannah
Conference walk to review any items. Call in advance. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
FIRE-Conference3/22/20173/22/20173/22/2017PCANC
DetailsJim Page
Conference rescheduled for 23MAR2017
BLD-Ceiling Grid Inspection3/20/20173/21/20173/21/2017PCANC
DetailsDave Hannah
Ceiling grid inspection after MEP sign offs. Call when on site.. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Conference3/20/20173/20/20173/20/2017PPASS
DetailsDave Hannah
Conference walk to review any items. Call in advance. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Conference3/16/20173/17/20173/17/2017PPASS
DetailsDave Hannah
Friday walk to review status. Call Adam When on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Conference3/16/20173/16/20173/16/2017PPASS
DetailsDave Hannah
Meet to discuss 1 side cover at Boise Centre West. Call Adam When on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson ok to one side rads wall ground level
BLD-Conference3/14/20173/14/20173/15/2017PPASS
DetailsDave Hannah
Adam Phone #: ###-####
BLD-Conference3/10/20173/10/20173/11/2017ADONE
DetailsDave Hannah
Walk with Adam call when on site Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in3/3/20173/3/20173/6/2017PPASS
DetailsDave Hannah
Stair 2 rated assemblies. Call Adam. thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in2/28/20173/1/20173/2/2017APASS
DetailsDave Hannah
Framing Inspection for cover of Stairs 1 and 2, concourse. Call Adam when on site. Thanks. akj. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection2/23/20172/24/20172/24/2017PDONE
DetailsDave Hannah
Request inspection of Above Grid work at escalator ceiling. Need to flood tiles in this area before the work platform is removed. Please call Adam when on site. AKJ ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection2/23/20172/24/20172/24/2017APASS
DetailsDave Hannah
Request inspection of Above Grid work at escalator ceiling. Need to flood tiles in this area before the work platform is removed. Please call Adam when on site. AKJ ###-#### Phone #: ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Conference2/19/20172/21/20172/21/2017APASS
DetailsMike Jordan
Inspection of framing at concourse. Call Adam when on site. Thx akj Phone #: ###-#### Inspection requested via web by Adam Johnson. Remaining framing at concourse ok to cover. Also verified insulation at "diving board".
BLD-Conference2/17/20172/17/20172/17/2017PCANC
DetailsJim Sly
Adam Phone #: ###-####
Contr. cancelled.
BLD-Conference2/16/20172/16/20172/16/2017PPART
DetailsDave Hannah
Meet to walk with Mike and Adam. Call when on site. ###-####. thanks akj Phone #: ###-#### Inspection requested via web by Adam Johnson ok to cover cieling ground level
BLD-Conference2/13/20172/13/20172/14/2017PPASS
DetailsDave Hannah
Walk with Hannah and look fireproofing above escalators. Call Adam when on site. ###-####. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in2/8/20172/9/20172/9/2017PPART
DetailsDave Hannah
Review framing. Walk with Adam and Koci. Call when on site, ###-####. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson . Part framing on second floor top of escalator soffits ok but need to spray fire proofing
BLD-Framing/Rough-in1/27/20171/27/20171/27/2017APASS
DetailsDave Hannah
Ongoing Framing inspection walk, weeks recap. Call Adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in1/17/20171/18/20171/20/2017APART
DetailsDave Hannah
Adam Phone #: ###-#### roof and soffit on elevated walk way west end ok
BLD-Framing/Rough-in1/13/20171/13/20171/13/2017PFAIL
DetailsDave Hannah
Adam Phone #: ###-#### soffit framing not per plan
BLD-Framing/Rough-in12/21/201612/22/201612/28/2016PPASS
DetailsDave Hannah
PM walk with Hannah to review SS Framing at Boise Centre. Please call Adam prior to site visit to coordinate location, etc. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Footing9/12/20169/13/20169/27/2016PPASS
DetailsDave Hannah
Footing inspection, multiple areas. Contact Ron when on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson also using mti for spec inspection and conc testing