BLD-Final | 11/8/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Dave Hannah
|
|
|
Corey Phone #: ###-####
|
FIRE-Final Inspection | 11/8/2017 | 11/8/2017 | 11/8/2017 | A | PASS |
Jim Page
|
|
|
Fire alarm panel integration complete for link, final life fire safety inspection passed/complete.
|
BLD-Aging Inspection | 9/25/2017 | 9/25/2017 | 10/2/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 7/6/2017 | 7/10/2017 | 7/11/2017 | P | PART |
Dave Hannah
|
|
|
Adam Phone #: ###-#### ok for perm after all other work and trades are finaled
|
FIRE-Final Inspection | 7/6/2017 | 7/10/2017 | 7/10/2017 | A | PART |
Jim Page
|
|
|
Life fire safety inspection complete with exception to the communication between fire panels with the link, TCO extension approved for 30 days in regards to life fire safey per conversation with Scott Arellano.
|
BLD-Aging Inspection | 6/19/2017 | 6/19/2017 | 6/20/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 3/30/2017 | 3/30/2017 | 3/31/2017 | A | PART |
Dave Hannah
|
|
|
Final walk am attempt. Call Adam. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for T.C.O.
|
FIRE-Final Inspection | 3/29/2017 | 3/30/2017 | 3/30/2017 | A | PART |
Jim Page
|
|
|
Partial life fire safety inspection complete for TCO requested area's (GBAD link, Century Link, Boise Center, escalator lobby levels 1 and 2, elevated concourse between Boise Center and west stairwell) Fire sprinklers are complete for TCO area, fire alarms are complete for TCO area, fire extinguishers are in place with current inspection tags.
|
BLD-Final | 3/27/2017 | 3/29/2017 | 3/29/2017 | P | CANC |
Dave Hannah
|
|
|
PM walk to review status. Call Adam before heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 3/27/2017 | 3/29/2017 | 3/29/2017 | P | CANC |
Jim Page
|
|
|
Scheduled for 8AM on 30MAR2017
|
BLD-Conference | 3/27/2017 | 3/28/2017 | 3/29/2017 | P | PASS |
Dave Hannah
|
|
|
PM walk to review status. Call Adam before heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/27/2017 | 3/27/2017 | 3/27/2017 | P | CANC |
Mike Jordan
|
|
|
PM walk to review status. Call Adam before heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/20/2017 | 3/24/2017 | 3/27/2017 | P | PART |
Dave Hannah
|
|
|
Conference walk to review any items. Call in advance. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson ext fire walls above fir doors
|
FIRE-Conference | 3/23/2017 | 3/23/2017 | 3/23/2017 | P | DONE |
Jim Page
|
|
|
Fire conference complete
|
FIRE-Conference | 3/22/2017 | 3/23/2017 | 3/23/2017 | A | CANC |
Jim Page
|
|
|
|
BLD-Conference | 3/20/2017 | 3/22/2017 | 3/23/2017 | P | PASS |
Dave Hannah
|
|
|
Conference walk to review any items. Call in advance. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
|
FIRE-Conference | 3/22/2017 | 3/22/2017 | 3/22/2017 | P | CANC |
Jim Page
|
|
|
Conference rescheduled for 23MAR2017
|
BLD-Ceiling Grid Inspection | 3/20/2017 | 3/21/2017 | 3/21/2017 | P | CANC |
Dave Hannah
|
|
|
Ceiling grid inspection after MEP sign offs. Call when on site.. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/20/2017 | 3/20/2017 | 3/20/2017 | P | PASS |
Dave Hannah
|
|
|
Conference walk to review any items. Call in advance. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/16/2017 | 3/17/2017 | 3/17/2017 | P | PASS |
Dave Hannah
|
|
|
Friday walk to review status. Call Adam When on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/16/2017 | 3/16/2017 | 3/16/2017 | P | PASS |
Dave Hannah
|
|
|
Meet to discuss 1 side cover at Boise Centre West. Call Adam When on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson ok to one side rads wall ground level
|
BLD-Conference | 3/14/2017 | 3/14/2017 | 3/15/2017 | P | PASS |
Dave Hannah
|
|
|
Adam Phone #: ###-####
|
BLD-Conference | 3/10/2017 | 3/10/2017 | 3/11/2017 | A | DONE |
Dave Hannah
|
|
|
Walk with Adam call when on site Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 3/3/2017 | 3/3/2017 | 3/6/2017 | P | PASS |
Dave Hannah
|
|
|
Stair 2 rated assemblies. Call Adam. thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 2/28/2017 | 3/1/2017 | 3/2/2017 | A | PASS |
Dave Hannah
|
|
|
Framing Inspection for cover of Stairs 1 and 2, concourse. Call Adam when on site. Thanks. akj. Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 2/23/2017 | 2/24/2017 | 2/24/2017 | P | DONE |
Dave Hannah
|
|
|
Request inspection of Above Grid work at escalator ceiling. Need to flood tiles in this area before the work platform is removed. Please call Adam when on site. AKJ ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | PASS |
Dave Hannah
|
|
|
Request inspection of Above Grid work at escalator ceiling. Need to flood tiles in this area before the work platform is removed. Please call Adam when on site. AKJ ###-#### Phone #: ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Conference | 2/19/2017 | 2/21/2017 | 2/21/2017 | A | PASS |
Mike Jordan
|
|
|
Inspection of framing at concourse. Call Adam when on site. Thx akj Phone #: ###-#### Inspection requested via web by Adam Johnson. Remaining framing at concourse ok to cover. Also verified insulation at "diving board".
|
BLD-Conference | 2/17/2017 | 2/17/2017 | 2/17/2017 | P | CANC |
Jim Sly
|
|
|
Adam Phone #: ###-#### Contr. cancelled.
|
BLD-Conference | 2/16/2017 | 2/16/2017 | 2/16/2017 | P | PART |
Dave Hannah
|
|
|
Meet to walk with Mike and Adam. Call when on site. ###-####. thanks akj Phone #: ###-#### Inspection requested via web by Adam Johnson ok to cover cieling ground level
|
BLD-Conference | 2/13/2017 | 2/13/2017 | 2/14/2017 | P | PASS |
Dave Hannah
|
|
|
Walk with Hannah and look fireproofing above escalators. Call Adam when on site. ###-####. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 2/8/2017 | 2/9/2017 | 2/9/2017 | P | PART |
Dave Hannah
|
|
|
Review framing. Walk with Adam and Koci. Call when on site, ###-####. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson . Part framing on second floor top of escalator soffits ok but need to spray fire proofing
|
BLD-Framing/Rough-in | 1/27/2017 | 1/27/2017 | 1/27/2017 | A | PASS |
Dave Hannah
|
|
|
Ongoing Framing inspection walk, weeks recap. Call Adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 1/17/2017 | 1/18/2017 | 1/20/2017 | A | PART |
Dave Hannah
|
|
|
Adam Phone #: ###-#### roof and soffit on elevated walk way west end ok
|
BLD-Framing/Rough-in | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | FAIL |
Dave Hannah
|
|
|
Adam Phone #: ###-#### soffit framing not per plan
|
BLD-Framing/Rough-in | 12/21/2016 | 12/22/2016 | 12/28/2016 | P | PASS |
Dave Hannah
|
|
|
PM walk with Hannah to review SS Framing at Boise Centre. Please call Adam prior to site visit to coordinate location, etc. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Footing | 9/12/2016 | 9/13/2016 | 9/27/2016 | P | PASS |
Dave Hannah
|
|
|
Footing inspection, multiple areas. Contact Ron when on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson also using mti for spec inspection and conc testing
|