BLD-Final | 11/15/2016 | 11/15/2016 | 11/15/2016 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | PART |
Phil Shearer
|
|
|
John Phone #: ###-####. OK for 30 day temp, Toilet flusher on wrong side of tank ADA bathroom
|
BLD-Final | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | FAIL |
Mike Jordan
|
|
|
John// please call ahead Phone #: ###-####. Provide ADA bathroom signs on wall at restroom, provide mirror in restroom, install the required vertical grab bars in restroom and provide flusher on turning side.
|
BLD-Final | 11/1/2016 | 11/2/2016 | 11/2/2016 | A | FAIL |
Mike Jordan
|
|
|
Cathy Phone #: ###-####. No city approved plans or review notes on site. Called Cathy to let her know. Will have to reschedule.
|
FIRE-Final Inspection | 10/21/2016 | 10/24/2016 | 10/24/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | FAIL |
Troy Cobbley
|
|
|
Provide occupant load sign, provide single action hardware on the restroom doors, mount the fire extinguishers, remove hardware from the west front door. Provide the fire review comments.
|
FIRE-Final Inspection | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | FAIL |
Troy Cobbley
|
|
|
Provide the fire life safety review comments, provide occupant load sign, provide panic hardware on front and back doors, provide exit discharge lighting at front and back doors, provide emergency lighting, provide single action hardware for the restroom doors, mount the fire extinguishers, disable and remove hardware on the west/front door as per approved plans.
|
BLD-Framing/Rough-in | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Roof trusses wrapped.
|
BLD-Framing/Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. Needs to wrap roof trusses going through 2hr. wall. Ecerything else ok.
|
BLD-Framing/Rough-in | 7/12/2016 | 7/12/2016 | 7/12/2016 | P | NR |
Jim Sly
|
|
|
John Phone #: ###-#### Called John and told him that an Electrical rough-in was performed.
|
BLD-Framing/Rough-in | 7/7/2016 | 7/8/2016 | 7/8/2016 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. All fire stopping completed on interior side.
|
BLD-Framing/Rough-in | 7/6/2016 | 7/7/2016 | 7/7/2016 | A | PASS |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Face layer of 5/8 type x ok. ok to to cover interior portion of wall with base layer.
|
BLD-Framing/Rough-in | 6/30/2016 | 6/30/2016 | 6/30/2016 | P | PASS |
Mike Jordan
|
|
|
Drywall inspection ###-#### John
|
BLD-Wall cover | 6/27/2016 | 6/28/2016 | 6/28/2016 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. interior side of 2hr. fire barrier. work in progress.
|
BLD-Framing/Rough-in | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | CANC |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Energy code compliance | 6/23/2016 | 6/23/2016 | 6/23/2016 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 6/10/2016 | 6/10/2016 | 6/10/2016 | P | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. contractor to follow approved plan for 2hr. fire barrieer walls,r provide new UL approved detail and show approved method for wood truss penetration.
|