Information based on query as of Thursday, June 20, 2024.
Permit Information
Permit NumberBLD16-00124
StatusFinaled
Name VERTICAL CORP
Site Address 1747 N FAIRMEADOW DR
Project NameVillage Charter School
Customer NumberBLD16-00161
ePlanReviewYes
Description
(VILLAGE CHARTER SCHOOL)(BLDG 1)Plan Modification to add partial fence on building 2 and change windows to be operable to meet ventilation requirments. Other minor changes made per plan modification applicaiton. All glazing shall be safety glazing as required by the IBC. **ajs**6/2/17*** Plan Modification to remove doors from class rooms as per the attached Building Official Occupant load approval. The occupant loads shall be posted and room layout posted. All conditons of approval shall be followed. **ajs**4/13/17**This project also being done in conjunction with BLD16-00161 on same set of plans. Remodel of an existing 24,500 sq. ft. office/retail building into new educational charter school with new classrooms and school administration offices per approved plans. New parking lot design and outdoor area for the kids. Work to include seismic upgrade from Risk Category II to Risk Category III, new interior walls, interior finish, fire sprinkler work, fire alarm work, plumbing work, mechanical work, and electrical work. Special Inspections required for structural steel, concrete and soils. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/6/201710/9/201710/9/2017APASS
DetailsJim Sly
Ron Phone #: ###-####
OK for Perm Occ.
BLD-Final8/16/20178/17/20178/17/2017APART
DetailsJim Sly
Ron Phone #: ###-####
OK for Temp Occ. OK for Perm Occ when Zoning signs Perm.
BLD-Final8/11/20178/14/20178/14/2017PCANC
DetailsJim Sly
Please check zoning signed off for temp too // Ron Phone #: ###-#### // called 10:10am 8-14-2017 Ron
FIRE-Final Inspection8/9/20178/9/20178/9/2017PPASS
DetailsTroy Cobbley
life safety passed. No gates/fence has been installed betwee building 1 and 2
BLD-Conference7/19/20177/20/20177/20/2017ADONE
DetailsJim Sly
Ron Phone #: ###-####
BLD-Framing/Rough-in5/31/20176/1/20176/1/2017ACANC
DetailsJim Sly
Ron-inspection is for the front of building amd canopy not for the plan modification Phone #: ###-####
BLD-Framing/Rough-in5/31/20176/1/20176/1/2017APASS
DetailsJim Sly
Ron-inspection is for the front of building amd canopy not for the plan modification Phone #: ###-####
East end Canopy on South wing framing....OK.
BLD-Energy code compliance5/12/20175/15/20175/15/2017APASS
DetailsJim Sly
Ron-bldg 1-Ron says plan mod doens''t have anything to do withg the frame or energy Phone #: ###-####
BLD-Framing/Rough-in5/12/20175/15/20175/15/2017APASS
DetailsJim Sly
Ron-bldg 1-Ron says plan mod doens''t have anything to do withg the frame or energy Phone #: ###-####
BLD-Energy code compliance5/5/20175/8/20175/8/2017PPART
DetailsJim Sly
Ron Phone #: ###-####
West Wing.......OK.
BLD-Framing/Rough-in5/5/20175/8/20175/8/2017PPART
DetailsJim Sly
Ron Phone #: ###-####
West Wing Framing Shear Walls and Energy Code.......OK.
BLD-Footing4/28/20175/2/20175/2/2017APART
DetailsJim Sly
Ron Wood Phone #: ###-####
Footings for Entry.......S.E. corner of complex OK pending MTI special insp, tests and approvals.
BLD-Energy code compliance4/20/20174/21/20174/21/2017PPASS
DetailsJim Sly
Insulation // Ron Phone #: ###-####
Engineer Provided Engineering for above and below braced wall line......Steel studs OK and and all framing OK per engineering....South wing.
BLD-Framing/Rough-in4/14/20174/17/20174/17/2017APART
DetailsMike Jordan
partial framing (n/a plan mod scope)// Ron Wood Phone #: ###-####. South wing framing only. ok to cover walls except for interior shear walls. Contractor needs additional details. Interior shear walls constructed of steel studs in leiu of wood studs. Needs to provide connections to underfloor as shown or provide alternate from engineer. Will also need additional detail for mech. ducts through CMU wall.