BLD-Final | 3/8/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Mike Jordan
|
|
|
Mark Phone #: ###-####. All issues resolved. Ok for perm cc.
|
BLD-Final | 3/8/2016 | 3/8/2016 | 3/8/2016 | P | PART |
Mike Jordan
|
|
|
OK for temp occ. Flushing mechanism on on toilet not on turning radius side. Plungers not yet installed in floor to lock doors in the open position.
|
BLD-Final | 3/4/2016 | 3/8/2016 | 3/8/2016 | A | CANC |
Mike Jordan
|
|
|
Mark Phone #: ###-####. mOved to pm.
|
FIRE-Final Inspection | 3/7/2016 | 3/7/2016 | 3/7/2016 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Main exit doors not installed yet
|
FIRE-Final Inspection | 3/4/2016 | 3/7/2016 | 3/7/2016 | A | FAIL |
Troy Cobbley
|
|
|
Provide fire extinguisher as discussed. Per contractor the office door is not being installed. Main exit doors and storefront glass is not on site yet. Smoke evac. system test passed
|
BLD-Framing/Rough-in | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | PART |
Mike Jordan
|
|
|
Mark Phone #: ###-####. Interior steel stud framed wall for restroom ok. Pending plumbing rough in inspection. Noted that wall already one sided with sheet rock when I arrived on site.
|
BLD-Wall cover | 2/17/2016 | 2/18/2016 | 2/18/2016 | A | PASS |
Mike Jordan
|
|
|
Mark Phone #: ###-####
|