BLD-Final | 12/9/2016 | 12/9/2016 | 12/9/2016 | P | PASS |
Mike Jordan
|
|
|
Wong Phone #: ###-####. All issues resolved. Ok for perm occ.
|
BLD-Final | 12/7/2016 | 12/9/2016 | 12/8/2016 | P | FAIL |
Mike Jordan
|
|
|
Hoang Phone #: ###-####. Provide ADA compliant restroom sign. Reflective surface for mirror to be 40 inches max above finish floor. Mount the tiolet paper dispenser per the approved plans. Provide ADA compliant POS. A portion of the WiFi bar to be ADA compliant per the approved plans. Plumbing final has also failed. A correction notice was posted.
|
FIRE-Final Inspection | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | DONE |
Troy Cobbley
|
|
|
I pointed out the need for a fire sprinkler permit for the required work. Looks like all of the existing uprights have been painted and many additional heads are needed.
|
BLD-Final | 9/20/2016 | 9/21/2016 | 9/21/2016 | A | CANC |
Mike Jordan
|
|
|
Santiago// please call ahead Phone #: ###-####
|
BLD-Framing/Rough-in | 9/21/2016 | 9/21/2016 | 9/21/2016 | A | PASS |
Mike Jordan
|
|
|
Santiago// please call ahead Phone #: ###-####. Framing for new opening in demissing wall ok.
|
BLD-Framing/Rough-in | 8/30/2016 | 8/31/2016 | 8/31/2016 | A | PASS |
Mike Jordan
|
|
|
Santiogo Phone #: ###-####. Interior steel stud framed walls and hardlid ok. Noted that fire sprinkler work not started.
|
BLD-Framing/Rough-in | 8/11/2016 | 8/12/2016 | 8/12/2016 | A | NR |
Mike Jordan
|
|
|
Santiago Phone #: ###-####. Needs MEP rough in inspections prior to framing inspection. Correction notice posted.
|