BLD-Final | 9/8/2016 | 9/9/2016 | 9/9/2016 | P | PASS |
Dave Hannah
|
|
|
would like call ahead; Ben Phone #: ###-####
|
BLD-Final | 8/24/2016 | 8/24/2016 | 8/24/2016 | A | PART |
Dave Hannah
|
|
|
Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen ok for temp occ
|
FIRE-Final Inspection | 8/24/2016 | 8/24/2016 | 8/24/2016 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, commercial hood fire suppression system inspection is complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | PASS |
Dave Hannah
|
|
|
Electrical grid inspection also called in for today PM. Please call Nic a half hour before inspection. Access to suite through back door in alley. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Conference | 7/8/2016 | 7/8/2016 | 7/8/2016 | A | PASS |
Dave Hannah
|
|
|
Interior framing. Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Wall cover | 6/28/2016 | 6/28/2016 | 6/28/2016 | A | PART |
Dave Hannah
|
|
|
Mechanical shafts fire taping. Please call Nic 1/2hr before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen int sheet rock ok
|
BLD-Framing/Rough-in | 6/21/2016 | 6/21/2016 | 6/22/2016 | P | PASS |
Dave Hannah
|
|
|
Roof platform and framing. If Nic not on site please call Ralph ###-#### or Karl ###-#### with Riverside (framers).Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Framing/Rough-in | 6/22/2016 | 6/22/2016 | 6/22/2016 | A | PASS |
Dave Hannah
|
|
|
Roof curb framing/bracing. Please call Nic when on site. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Conference | 6/17/2016 | 6/17/2016 | 6/17/2016 | A | DONE |
Dave Hannah
|
|
|
To discuss ''shaft'' fire rated wall/ceiling assembly. Please call 15 minutes before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
|
BLD-Framing/Rough-in | 6/15/2016 | 6/15/2016 | 6/15/2016 | A | CANC |
Dave Hannah
|
|
|
Mech shaft framing. Please call Nic 1/2 hr before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen part basement walls ok to cover
|