BLD-Conference | 12/27/2019 | 12/31/2019 | 12/31/2019 | A | DONE |
Tell Riley
|
|
|
no response from owner to call last week//permit will expire//
|
BLD-Conference | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | DONE |
Tell Riley
|
|
|
Check on activity onsite//left message with contact to call regarding permit, still needs final for electrical as well//
|
BLD-Aging Inspection | 12/26/2019 | 12/26/2019 | 12/26/2019 | | CANC |
Tell Riley
|
|
|
|
BLD-Aging Inspection | 12/25/2019 | 12/25/2019 | 12/26/2019 | | CANC |
Tell Riley
|
|
|
|
BLD-Aging Inspection | 8/13/2019 | 8/13/2019 | 8/13/2019 | | PASS |
Tell Riley
|
|
|
Extension request counts as all three extension requests since no activity or request for extension has occurred since November of 2016. This is the final extension of 180 days. A passed required inspection needs to occur within 180 days in order to update the permit or the project needs to be completed and finaled within 180 days.4/1/2019 DONE Details Jason Blais
|
BLD-Foundation | 6/20/2016 | 6/20/2016 | 6/20/2016 | P | CANC |
Phil Shearer
|
|
|
Jeremy Phone #: ###-####
|
BLD-Final | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | NR |
Jim Sly
|
|
|
Avery Phone #: ###-#### Need Electr final.
|
BLD-Framing/Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PASS |
Jim Sly
|
|
|
Avery Phone #: ###-####
|
BLD-Footing | 5/5/2016 | 5/6/2016 | 5/6/2016 | P | PASS |
Jim Sly
|
|
|
Avery Phone #: ###-#### Mono pour footing/slab.
|