BLD-Final | 12/12/2016 | 12/12/2016 | 12/12/2016 | P | PASS |
Jim Sly
|
|
|
Jam Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 12/6/2016 | 12/6/2016 | 12/8/2016 | P | PART |
Jim Sly
|
|
|
Beniton Phone #: ###-#### OK for Temp Occ. OK for Perm Occ. when.....2 separate exit doors at North side of Bldg have double keyed locks with indicators installed.
|
FIRE-Supply Line Hydro | 12/7/2016 | 12/8/2016 | 12/8/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PART |
Troy Cobbley
|
|
|
A fire watch is to be inplace as per Fire Dept and the contractor discussion for tonight. I'm scheduled for a final re-inspection for tomorrow morning for the testing of the two duct smoke detectors. Jim Sly is going to cover the main exit door hardware. I need to verify with the Fire Dept that all items for their tank inspection have be addressed. All other items appear ok.
|
BLD-Ceiling Grid Inspection | 11/18/2016 | 11/21/2016 | 11/21/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Jan Tietjen
|
BLD-Energy code compliance | 10/20/2016 | 10/21/2016 | 10/21/2016 | P | PASS |
Jim Sly
|
|
|
Jam Phone #: ###-####
|
BLD-Framing/Rough-in | 10/19/2016 | 10/19/2016 | 10/19/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Jan Tietjen
|
BLD-Energy code compliance | 10/4/2016 | 10/5/2016 | 10/5/2016 | A | PART |
Jim Sly
|
|
|
Jan Phone #: ###-#### Walls behind coolers ......OK.
|
BLD-Wall Bracing | 9/30/2016 | 10/3/2016 | 10/3/2016 | P | PASS |
Jim Sly
|
|
|
Dan Phone #: ###-####
|
BLD-Conference | 9/26/2016 | 9/26/2016 | 9/26/2016 | P | DONE |
Jim Sly
|
|
|
Jam Phone #: ###-#### Walk Thru with Jan........Strata hired to do all special inspections.Exterior walls and roof framing almost complete.....went over wall bracing.
|
BLD-Foundation | 8/22/2016 | 8/23/2016 | 8/23/2016 | P | PASS |
Jim Storey
|
|
|
Janan Phone #: ###-#### placed w si
|
BLD-Foundation | 8/17/2016 | 8/18/2016 | 8/18/2016 | A | PEND |
Jim Sly
|
|
|
Late morning .......Rebar // Jay Phone #: ###-#### Inspection of Footings for entire building. STRATA will be doing all special inspections. OK to pour with approval from STRATA and Stamped Approved plans are on site. No approved planson site at this time.
|
BLD-Footing | 8/12/2016 | 8/15/2016 | 8/15/2016 | A | PASS |
Mike Jordan
|
|
|
Jan-rebar-pour time 2:30 Phone #: ###-####. column footings for canopy. Will have special inspection.
|