BLD-Final | 7/6/2016 | 7/12/2016 | 7/12/2016 | A | PASS |
Jim Sly
|
|
|
would like call ahead; Dave Phone #: ###-####
|
BLD-Final | 7/5/2016 | 7/6/2016 | 7/6/2016 | A | NH |
Mike Jordan
|
|
|
Dave Phone #: ###-####. No one at place of bussiness. Doors locked. Still needs plumbing.
|
BLD-Final | 6/16/2016 | 6/16/2016 | 6/16/2016 | P | PART |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Ok for temp occ. Provide occ. sensors were required. Pocket door has been made inapporable. PLumbing is on temp as well.
|
FIRE-Final Inspection | 6/16/2016 | 6/16/2016 | 6/16/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Owner is going to make the pocket door in-operative instead of supply ADA hardware on it.
|
BLD-Final | 6/15/2016 | 6/16/2016 | 6/16/2016 | A | NR |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Needs fire/life/safety inspection.
|
BLD-Framing/Rough-in | 5/20/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | NR |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Doors locked, no ine here, no access. Will need to reschedule.
|
BLD-Conference | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | DONE |
Mike Jordan
|
|
|
stop by project to check on progress, all MEP rough in inspections are completed. Framing is completed and majority covered. Also noted clearance issue with restroom door, side approach latch side, pull. Aslo noted elevated platform constructed that is not on plans. Tenant is removing some shhet rock for inspection, moving door to meet min clearance and will insulate under platform and then call in for frming inspection.
|