Information based on query as of Wednesday, June 19, 2024.
Permit Information
Permit NumberBLD16-01003
StatusFinaled
Name HIGHLAND HOMES LLC
Site Address 5820 W HILL RD
Project NameMichaud
Customer Number 
ePlanReviewYes
Description
WUI Zone A; Permit for the construction of a new 3399 sq. ft., two story (first story 816 sq. ft., second story 1296 sq. ft., third story 1287 sq. ft.) single family dwelling with 4 bedrooms, 3.5 bathrooms, approximately 320 sq. ft. of balcony, 70 sq. ft. covered porch, 210 sq. ft. sunroom, 210 sq. ft. covered car port and a 545 sq. ft. attached garage per the approved plans, engineering, ACCA report and any notations. R-1C zoning and setbacks per planning.//leg ***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/9/201612/9/201612/9/2016PPASS
DetailsJim Sly
jared Phone #: ###-####
DOC - Permit Finaled12/9/201612/9/201612/9/2016PPASS
DetailsJim Sly
BLD-Final12/6/201612/7/201612/7/2016PNR
DetailsJim Sly
Jared Phone #: ###-####
Still need Fire final inspection........
BLD-Final12/5/201612/6/201612/6/2016PNR
DetailsJim Sly
jared Phone #: ###-####
Need Fire final OK and complete previous correction notice. Called Jared....left V/mssg.
BLD-Final12/2/201612/5/201612/5/2016PNR
DetailsTony Young
jared Phone #: ###-####,, not all done
BLD-Final12/2/201612/5/201612/5/2016ANR
DetailsTony Young
jared Phone #: ###-####
BLD-Final12/1/201612/2/201612/2/2016PNR
DetailsTony Young
jared Phone #: ###-####,, conf walk through only,, correction notice posted,, need trades,, blower door test,, fire cailking,, temp glass,, stairs per code,, roof completed,, etc.
BLD-Energy code compliance9/27/20169/29/20169/29/2016PPASS
DetailsJim Sly
Jared Phone #: ###-####
BLD-Energy code compliance9/20/20169/21/20169/21/2016ANR
DetailsJim Sly
Jared Phone #: ###-####
Talked to Jared. Notified at frame insp. that Sprinklers not inspected yet. Still no inspection at Energy Code inspection. No approval for cover.
BLD-Framing/Rough-in9/14/20169/15/20169/15/2016PPASS
DetailsJim Sly
Jared Phone #: ###-####
BLD-Framing/Rough-in9/9/20169/12/20169/12/2016PNR
DetailsJim Storey
would like call ahead; Jared Phone #: ###-#### beam to floor joist/ gyp cans/ nuts portal
BLD-Wall Bracing8/24/20168/25/20168/25/2016APASS
DetailsTony Young
Phone #: 4404356 >> Inspection requested via mobile web by Eric,, exterior shear ok
BLD-Wall Bracing8/22/20168/23/20168/23/2016AFAIL
DetailsTony Young
Phone #: 4404356 >> Inspection requested via mobile web by Eric Atwood,, need to finish per plan,, recall
BLD-Foundation6/24/20166/24/20166/24/2016APASS
DetailsPhil Shearer
Phone #: 2089616103 >> Inspection requested via mobile web by Alva Ponce
BLD-Footing6/23/20166/23/20166/23/2016PPASS
DetailsPhil Shearer
Alvaro-says soil report was emailed to Tony Y Phone #: ###-####
BLD-Footing6/22/20166/22/20166/22/2016PPEND
DetailsTony Young
Advardo Phone #: ###-####,, ok pending soils report approval,, ok to pour after