BLD-Final | 6/6/2018 | 6/6/2018 | 6/7/2018 | P | PASS |
Jim Sly
|
|
|
for perm occ pass on structural OK for Perm. Occ.
|
FIRE-Final Inspection | 5/23/2018 | 5/24/2018 | 5/24/2018 | P | PASS |
Jim Page
|
|
|
Remaining items have been addressed, final life fire safety inspection complete.
Reinspection for Final sign off from TCO Phone #: ###-#### Inspection requested via web by shaun carley
|
BLD-Final | 4/30/2018 | 5/1/2018 | 5/2/2018 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by shaun carley OK for Temp Occ. OK for Perm Occ. when Fire and Zoning signs off for Perm.
|
FIRE-Final Inspection | 4/30/2018 | 5/1/2018 | 5/1/2018 | P | PART |
Jim Page
|
|
|
Partial life fire safety inspection for tco complete (30 day TCO per conversation with Ron Johnson) Fire sprinkler inspection complete, fire alarm inspection complete, fire exitnguishers are in place and will get inspection tags installed before final inspection. Items that need to be completed before final is a knox box installed by front entry and emergency evacuation plan for each unit, items will be verified before final C of O
|
BLD-Final | 4/27/2018 | 4/30/2018 | 4/30/2018 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by shaun carley Inspection cancelled from web by: shaun carley
|
BLD-Ceiling Grid Inspection | 3/21/2018 | 3/21/2018 | 3/21/2018 | P | PASS |
Jim Sly
|
|
|
above ceiling grid inspection on the 2nd and 3rd floor corridors. Phone #: ###-#### Inspection requested via web by shaun carley
|
BLD-Ceiling Grid Inspection | 3/5/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Jim Sly
|
|
|
Above grid inspection in corridors on the 5th and 4th floors. Shaft liner inspection for trash chute in elevator lobbies. Phone #: ###-#### Inspection requested via web by shaun carley
|
BLD-Ceiling Grid Inspection | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | PASS |
Jim Sly
|
|
|
Fire caulk inspection in the drops in units 309-319 Phone #: ###-#### Inspection requested via web by shaun carley
|
BLD-Ceiling Grid Inspection | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PASS |
Jim Sly
|
|
|
Inspect above grid in units 209,210,211,212,213,214,215,216,217,218, and 219. Phone #: ###-#### Inspection requested via web by shaun carley
|
BLD-Other | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PASS |
Jim Sly
|
|
|
Fire caulk inspection in drops units 409-419 and corridor building 1. Phone #: ###-#### Inspection requested via web by shaun carley
|
BLD-Other | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | CANC |
Brandon Shaw
|
|
|
fire caulk in drops for units 409-419 and 4th floor corridor // Shaun ###-####
|
BLD-Framing/Rough-in | 12/20/2017 | 12/21/2017 | 12/21/2017 | A | PASS |
Jim Sly
|
|
|
drops units 509-519 Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Sly
|
|
|
Units 201-208 framed drops Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 11/14/2017 | 11/15/2017 | 11/15/2017 | A | PASS |
Jim Sly
|
|
|
Units 409-419 ready to insulate. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 11/10/2017 | 11/13/2017 | 11/13/2017 | A | PASS |
Jim Sly
|
|
|
Drop Ceilings units 301-308 Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 10/31/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Jim Sly
|
|
|
North and South Stair Towers and Level 4 drop ceiling areas units 401-408 Phone #: ###-#### Inspection requested via web by Michael West
|
FIRE-Conference | 10/26/2017 | 10/27/2017 | 10/27/2017 | P | DONE |
Troy Cobbley
|
|
|
Tenting of sprinkler lines in units 509-519 passed. Numerous corrections made while I was on site. I also made an entry in the project related fire sprinkler permit activites.
|
BLD-Framing/Rough-in | 10/20/2017 | 10/20/2017 | 10/20/2017 | A | PASS |
Jim Sly
|
|
|
Units 501-508 fur down ceilings Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 10/13/2017 | 10/16/2017 | 10/17/2017 | P | PASS |
Jim Sly
|
|
|
Units 209-219 Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | PASS |
Jim Sly
|
|
|
Units 509-519 ready to insulate. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Energy code compliance | 10/5/2017 | 10/9/2017 | 10/9/2017 | A | NR |
Jim Sly
|
|
|
units 209-219 // Matt Fletcher Phone #: ###-####
|
BLD-Framing/Rough-in | 10/5/2017 | 10/9/2017 | 10/9/2017 | A | NR |
Jim Sly
|
|
|
units 209-219 // Matt Fletcher Phone #: ###-####
|
BLD-Framing/Rough-in | 9/19/2017 | 9/19/2017 | 9/19/2017 | A | PASS |
Jim Sly
|
|
|
Level 2 Corridor Ceiling to pre-rock Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 9/8/2017 | 9/8/2017 | 9/11/2017 | P | PASS |
Jim Sly
|
|
|
Units 201-208 ready to insulate Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | PASS |
Jim Sly
|
|
|
Units 301-308 Ready for insulation. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 8/23/2017 | 8/23/2017 | 8/23/2017 | P | PASS |
Jim Sly
|
|
|
Units 401-408 Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | PASS |
Jim Sly
|
|
|
Units 501-508 ready to insulate. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PART |
Jim Sly
|
|
|
Elevator shaft Phone #: ###-#### Inspection requested via web by Michael West Elevator shaft OK to cover.
|
BLD-Conference | 7/18/2017 | 7/18/2017 | 7/18/2017 | P | CANC |
Jim Sly
|
|
|
|
BLD-Conference | 6/29/2017 | 6/29/2017 | 6/29/2017 | P | PASS |
Jim Sly
|
|
|
Mike West Phone #: ###-####
|
BLD-Concrete | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Phil Shearer
|
|
|
walls and footings Phone #: ###-#### Inspection requested via web by Michael West
|