BLD-Final | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PASS |
Jim Sly
|
|
|
looks like everyone has signed off but you only have a partial final OK for perm Occ.
|
BLD-Aging Inspection | 4/17/2018 | 4/17/2018 | 4/23/2018 | | CANC |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 2/14/2018 | 2/14/2018 | 2/15/2018 | | DONE |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Final | 12/4/2017 | 12/4/2017 | 12/4/2017 | A | PART |
Jim Sly
|
|
|
Late Morning Please. Phone #: ###-#### Inspection requested via web by Michael West OK for Temp. Occ. OK for Perm. Occ. When Electr, Mech, Plumb and Zoning signs for Perm Occ.
|
FIRE-Final Inspection | 12/4/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Jim Page
|
|
|
Building 2 fire sprinkler inspection complete, building 2 fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is located by main entry. Final life fire safety inspection for buidling 2 passed/complete.
|
FIRE-Final Inspection | 11/30/2017 | 12/1/2017 | 12/1/2017 | A | FAIL |
Jim Page
|
|
|
Fire alarm modifications not completed at time of inspection, life fire safety inspection stopped.
|
FIRE-Alarm Testing | 11/30/2017 | 12/1/2017 | 12/1/2017 | A | CANC |
Jim Page
|
|
|
Fire alarm testing/inspection is to be requested by the installing contractor under the associated FIR permit, this request is cancelled.
|
FIRE-Final Inspection | 11/30/2017 | 11/30/2017 | 11/30/2017 | A | FAIL |
Jim Page
|
|
|
Need 18 inches of clearance from bottom of fire sprinkler deflector to top of storage (closets and pantries are the main issue). No exterior signage for roof access or fire sprinkler riser room. Provide emergency lighting for exit discharge landings. FIR permits for both fire sprinkler and fire alarm need to be finaled before life fire safety inspection can be completed.
|
BLD-Final | 11/30/2017 | 11/30/2017 | 11/30/2017 | A | PEND |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Michael West Pre-inspection....walk thru.
|
BLD-Ceiling Grid Inspection | 11/10/2017 | 11/13/2017 | 11/13/2017 | A | PASS |
Jim Sly
|
|
|
Level 5 and Level 4 Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 11/3/2017 | 11/3/2017 | 11/3/2017 | P | PART |
Brandon Shaw
|
|
|
Level 1 elevator lobby.
OK to cover
|
BLD-Framing/Rough-in | 9/21/2017 | 9/22/2017 | 9/22/2017 | A | PASS |
Jim Sly
|
|
|
Units 211-220 drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | PASS |
Jim Sly
|
|
|
Elevator lobby ceilings at levels 2 and 3. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | PASS |
Jim Sly
|
|
|
Units 311-320 Drop Ceilings Ready to cover. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 9/1/2017 | 9/1/2017 | 9/1/2017 | P | NR |
Jim Sly
|
|
|
Units 311-320 Drop Ceilings and Soffits Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 8/24/2017 | 8/24/2017 | 8/24/2017 | P | PASS |
Jim Sly
|
|
|
Units 411-420 soffits and drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 8/16/2017 | 8/16/2017 | 8/17/2017 | P | PASS |
Jim Sly
|
|
|
Units 511-520 Soffits and drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 8/14/2017 | 8/14/2017 | 8/14/2017 | P | NR |
Jim Sly
|
|
|
Units 511-520 Soffits and Drops to cover with gyp-board. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Jim Sly
|
|
|
Units 201-210 Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Conference | 7/18/2017 | 7/18/2017 | 7/18/2017 | P | CANC |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 7/14/2017 | 7/14/2017 | 7/17/2017 | P | PART |
Brandon Shaw
|
|
|
Level 3 drop ceilings Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Energy code compliance | 6/29/2017 | 6/29/2017 | 6/29/2017 | P | PASS |
Jim Sly
|
|
|
Mike West Phone #: ###-####
|
BLD-Energy code compliance | 6/29/2017 | 6/29/2017 | 6/29/2017 | A | PART |
Brandon Shaw
|
|
|
Units 411-420 insulation
|
BLD-Framing/Rough-in | 6/21/2017 | 6/21/2017 | 6/21/2017 | P | PART |
Brandon Shaw
|
|
|
Units 511-520 Framing Phone #: ###-#### Inspection requested via web by Michael West Units 511-520
|
BLD-Framing/Rough-in | 6/7/2017 | 6/7/2017 | 6/7/2017 | P | PART |
Jim Sly
|
|
|
Mike Phone #: ###-#### 3rd level OK.
|
BLD-Framing/Rough-in | 6/1/2017 | 6/2/2017 | 6/2/2017 | A | PASS |
Jim Sly
|
|
|
UNits 211- thru 220 - Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 5/31/2017 | 5/31/2017 | 5/31/2017 | P | NR |
Jim Sly
|
|
|
Units 211-220 ready to insulate. Phone #: ###-#### Inspection requested via web by Michael West Electr. needs to complete firestopping.
|
BLD-Energy code compliance | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Jim Sly
|
|
|
Level 3 units 301-310 Insulation ready for GWB install. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 4/25/2017 | 4/25/2017 | 4/25/2017 | P | PART |
Jim Sly
|
|
|
Units 301-310 Ready to insulate. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 4/18/2017 | 4/18/2017 | 4/18/2017 | P | PASS |
Jim Sly
|
|
|
Level 4 units 401-410 framing. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Wall cover | 4/13/2017 | 4/13/2017 | 4/13/2017 | P | PASS |
Jim Sly
|
|
|
Units 501-510 Insulation Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 4/4/2017 | 4/5/2017 | 4/5/2017 | A | PART |
Jim Sly
|
|
|
Level 5 units 501-510 Framing for insulation to start Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Framing/Rough-in | 3/2/2017 | 3/2/2017 | 3/2/2017 | A | PART |
Jim Sly
|
|
|
Pre-rock corridor ceilings and 4'' down the wall at levels 2,3,4 and 5 West half of building. Phone #: ###-#### Inspection requested via web by Michael West OK
|
BLD-Framing/Rough-in | 2/28/2017 | 2/28/2017 | 2/28/2017 | P | PART |
Jim Sly
|
|
|
Pre-rock at tubs for units 501-510 and 401-410. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Wall Bracing | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PART |
Mike Jordan
|
|
|
Shear walls Units401-410 Phone #: ###-#### Inspection requested via web by Michael West. Interior shear walls for corrido walls at first floor. Nailing ok. Needs to install holdowns.
|
BLD-Framing/Rough-in | 2/15/2017 | 2/16/2017 | 2/16/2017 | A | PART |
Jim Sly
|
|
|
Roof sheathing and level 5 units 501-510 shearwall nailing. Phone #: ###-#### Inspection requested via web by Michael West OK pending MTI special inspections, tests and approvals.
|
BLD-Conference | 2/13/2017 | 2/14/2017 | 2/15/2017 | A | PEND |
Bob Archibald
|
|
|
Requesting an inspection to clarify whether the use of a generator for elevator operation in the event of a power failure is required, or if a battery backup lowering function is sufficient to meet code. Phone #: ###-#### Inspection requested via web by Michael West. Backup Power question under review.
|
BLD-Conference | 1/27/2017 | 1/31/2017 | 2/13/2017 | A | NR |
Dave Hannah
|
|
|
Consultation to discuss inspections as we move into the framing and finishes stages. Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Conference | 12/13/2016 | 12/13/2016 | 12/13/2016 | P | DONE |
Phil Shearer
|
|
|
Phone #: 8013815319 >> Inspection requested via mobile web by Mike west
|