BLD-Final | 3/15/2017 | 3/16/2017 | 3/16/2017 | P | PASS |
Jim Sly
|
|
|
Ian Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 1/19/2017 | 1/20/2017 | 1/20/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Opticon tested and verified by Boise Fire. Contractor stated the side emergency gate has a Knox key and will be locked when snow can be cleared.
|
BLD-Final | 1/18/2017 | 1/19/2017 | 1/19/2017 | A | PART |
Jim Sly
|
|
|
temp on Fire, life/ safety . waiting for fire truck to test Opticom function. Phone #: ###-#### Inspection requested via web by J.C. Murray OK for Temp Occ. OK for Perm Occ. when Zoning and Fire signs Perm.
|
FIRE-Final Inspection | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given until the Opticon for the main gate is verified by the Boise Fire Dept as functional. I let the contractor know that the gate is not to be used until it is functional. I spoke to the gate installer and the Opticon should be installed by tomorrow morning and tested in the afternoon.
|
FIRE-Final Inspection | 1/16/2017 | 1/17/2017 | 1/17/2017 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled and the exit discharge light over the main exit repaired. I also discussed the need for the Opticom for the electric main gate prior to a final sign off for the entire project. See note 13 of the building A review comments.
|
BLD-Ceiling Grid Inspection | 1/12/2017 | 1/12/2017 | 1/12/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by J.C. Murray
|
FIRE-Conference | 1/12/2017 | 1/12/2017 | 1/12/2017 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the general contractor about getting the fire hydrant located along Eagle Rd rotated as per the approved drawings. He was going to follow up with Suez.
|
BLD-Energy code compliance | 11/4/2016 | 11/7/2016 | 11/7/2016 | A | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### Firestop penitrations 3 hr wall.
|
BLD-Footing | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | PASS |
Jim Sly
|
|
|
Jake Phone #: ###-#### Sign.
|
BLD-Framing/Rough-in | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### 3 hr wall at office area
|
BLD-Other | 9/26/2016 | 9/27/2016 | 9/27/2016 | A | NR |
Jim Sly
|
|
|
Jake// 3hr firewall inspection Phone #: ###-#### Contractor to provide detail for 3 hr wall and UL listed/tested assembly.
|
BLD-Framing/Rough-in | 9/15/2016 | 9/16/2016 | 9/16/2016 | A | PASS |
Jim Sly
|
|
|
Milton Phone #: ###-####
|
BLD-Concrete | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | PASS |
Jim Sly
|
|
|
Milton Phone #: ###-#### OK pending MTI special Insp, tests and approvals.
|
BLD-Foundation | 8/12/2016 | 8/15/2016 | 8/15/2016 | P | PEND |
Tony Young
|
|
|
Milton Phone #: ###-####,, slab,, pending special inspection report
|
BLD-Foundation | 8/10/2016 | 8/11/2016 | 8/11/2016 | P | PART |
Jim Sly
|
|
|
walton Phone #: ###-#### Remaining walls at East Bldg OK pending MTI special insp, tests and approvals.
|
BLD-Wall Bracing | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | PART |
Jim Sly
|
|
|
Mitchem Phone #: ###-#### Should be foundation wall. Closest wall to Eagle road. OK pending MTI special insp, tests and approvals.
|
BLD-Footing | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | PART |
Jim Sly
|
|
|
Milton Phone #: ###-#### Area closest to Eagle Rd. OK Pending MTI special inspection, tests and approvals.
|