BLD-Final | 3/15/2017 | 3/16/2017 | 3/16/2017 | P | PASS |
Jim Sly
|
|
|
Ian Phone #: ###-#### OK for Perm Occ.
|
BLD-Aging Inspection | 3/14/2017 | 3/14/2017 | 3/16/2017 | | CANC |
Jim Sly
|
|
|
|
BLD-Final | 1/12/2017 | 1/12/2017 | 1/12/2017 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by J.C. Murray
**Needs Zoning approval first 1/13/17 C_P**
|
BLD-Final | 1/5/2017 | 1/6/2017 | 1/6/2017 | A | NR |
Jim Sly
|
|
|
jake Phone #: ###-#### Need Mech Final.
|
FIRE-Final Inspection | 1/3/2017 | 1/4/2017 | 1/4/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | NR |
Jim Sly
|
|
|
jake Phone #: ###-#### Need Fire Final.
|
FIRE-Final Inspection | 12/8/2016 | 12/8/2016 | 12/8/2016 | P | FAIL |
Troy Cobbley
|
|
|
need to repair the exit discharge lights and clear the fire dept access
|
BLD-Framing/Rough-in | 10/26/2016 | 10/27/2016 | 10/27/2016 | A | PASS |
Jim Sly
|
|
|
Jake Phone #: ###-####
|
BLD-Foundation | 8/24/2016 | 8/25/2016 | 8/26/2016 | P | PART |
Jim Sly
|
|
|
Milton Phone #: ###-#### Select footing/slab OK Pending MTI special inspections, tests and approvals.
|