BLD-Final | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Mike Jordan
|
|
|
Gordon Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 | A | PASS |
Jim Page
|
|
|
Short wall PIV in place and operational, final life fire safety inspection passed/complete.
|
BLD-Final | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PART |
Mike Jordan
|
|
|
gordon Phone #: ###-####. Ok for temp. occ.
|
BLD-Final | 11/30/2016 | 12/1/2016 | 12/1/2016 | A | NR |
Mike Jordan
|
|
|
Needs mech. final inspection and will also need to remove tile from grid ceiling for grid inspection.
|
FIRE-Final Inspection | 11/30/2016 | 12/1/2016 | 12/1/2016 | A | PART |
Troy Cobbley
|
|
|
A temporary for the life safety is being given until the new PIV has been installed which is scheduled to arrive on 12/7/16
|
BLD-Final | 11/28/2016 | 11/30/2016 | 11/30/2016 | P | NR |
Mike Jordan
|
|
|
Gordan Phone #: ###-####. rescheduled for a.m. inspection 12-1-16.
|
FIRE-Final Inspection | 11/29/2016 | 11/30/2016 | 11/30/2016 | A | FAIL |
Troy Cobbley
|
|
|
Provide final inspections for the project related fire alarm and fire sprinkler permits, Provide occupant load sign and provide clearance at the FDC of 36" as discussed and as directed by the fire dept.
|
BLD-Footing | 10/31/2016 | 11/1/2016 | 11/1/2016 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####. Footing infill at south side of building were existing transformer was located. Will have special inspection on epoxy for rebar.
|
BLD-Energy code compliance | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####
|
BLD-Framing/Rough-in | 10/7/2016 | 10/10/2016 | 10/10/2016 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####
|
BLD-Energy code compliance | 9/29/2016 | 9/30/2016 | 9/30/2016 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####. Exterior walls behind cooler/freezer combos only.
|
BLD-Wall Bracing | 9/26/2016 | 9/27/2016 | 9/27/2016 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####. Exterior shear walls and all hold downs ok. ok to ocver exterior.
|
BLD-Wall Bracing | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Phil Shearer
|
|
|
Roof nailing - Rick Phone #: ###-####
|
BLD-Framing/Rough-in | 9/20/2016 | 9/21/2016 | 9/21/2016 | P | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####Truss to ledger connections.
|
BLD-Framing/Rough-in | 9/19/2016 | 9/20/2016 | 9/20/2016 | P | CANC |
Mike Jordan
|
|
|
Rick Phone #: ###-####
|
BLD-Concrete | 8/26/2016 | 8/29/2016 | 8/29/2016 | P | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####
|
BLD-Foundation | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PART |
Mike Jordan
|
|
|
Rick Phone #: ###-####. Work in progress. Will have special inspection. Ok to place concrete after special inspection approval.
|