FIRE-Final Inspection | 10/11/2017 | 10/12/2017 | 10/11/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Tim Phone #: ###-####
|
FIRE-Final Inspection | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | CANC |
Troy Cobbley
|
|
|
Opticon was non-functional.
Tim Sanders Phone #: ###-####
|
BLD-Final | 7/12/2017 | 7/13/2017 | 7/13/2017 | P | PASS |
Mike Jordan
|
|
|
Zoning hasn''t signed off yet // Amber Phone #: ###-####. All issues resolved. Will be ok for perm occ. once zoning signs perm.
|
BLD-Final | 6/23/2017 | 6/26/2017 | 6/26/2017 | A | PART |
Mike Jordan
|
|
|
Tim Sanders Phone #: ###-####. Provide ADA hardware on pocket door on restroom door. Provide single action on offfice door hardware and server room door. ok for temp occ.
|
FIRE-Final Inspection | 6/23/2017 | 6/23/2017 | 6/23/2017 | P | PASS |
Jim Page
|
|
|
Final inspection for fire life safety passed/complete
|
FIRE-Final Inspection | 6/20/2017 | 6/21/2017 | 6/21/2017 | P | PART |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, emergency lighting operational to include exit discharge, property has knox box installed by main entry of office, thumbturn deadbolt between storage untis and office removed at time of inspection. Signage will be installed over main entry reading "Door to remain unlocked while occupied". Partial final inspection complete for life fire safety, last remaining item is the opticon system for vehicle gate, life fire safety can be finaled after the responding fire station tests the opticon system for correct operation.
|
BLD-Energy code compliance | 3/23/2017 | 3/24/2017 | 3/24/2017 | A | PASS |
Mike Jordan
|
|
|
would like call ahead; Jay Phone #: ###-####
|
BLD-Framing/Rough-in | 3/24/2017 | 3/24/2017 | 3/24/2017 | A | PASS |
Mike Jordan
|
|
|
would like call ahead; Jay Phone #: ###-####
|
BLD-Framing/Rough-in | 3/16/2017 | 3/16/2017 | 3/16/2017 | P | PART |
Mike Jordan
|
|
|
Jay Phone #: ###-####. Ok to insulate. Install the missing lateral brace on B6 truss, Install the straps on the 2ply girder truss as shown and install the draft stop. Provide city set of approved plans.
|
BLD-Wall Bracing | 3/16/2017 | 3/16/2017 | 3/16/2017 | P | PASS |
Mike Jordan
|
|
|
Jay Phone #: ###-####. Interior wall bracing ok. All holdowns ok. All previous missing holdowns installed, reviewed special inspection report, ok.
|
BLD-Wall Bracing | 2/28/2017 | 3/1/2017 | 3/1/2017 | P | PASS |
Mike Jordan
|
|
|
Jay Phone #: ###-####. Exterior wall bracing only ok.
|
BLD-Wall Bracing | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | FAIL |
Mike Jordan
|
|
|
Jay Phone #: ###-####. Provide staple conversion. Install all holdowns, missing blocking and fasten all missed areas. Correction notice posted.
|
BLD-Foundation | 9/22/2016 | 9/22/2016 | 9/22/2016 | P | PART |
Mike Jordan
|
|
|
Jason-pour time 4:00 Phone #: ###-####. Work in progress. Specia inspector wil be on site.
|
BLD-Footing | 9/20/2016 | 9/21/2016 | 9/21/2016 | P | PART |
Mike Jordan
|
|
|
2:30 pour; Jason Phone #: ###-####. Work in progress on installing remaining verts. Special inspector on site.
|