BLD-Final | 11/3/2016 | 11/3/2016 | 11/3/2016 | A | PASS |
Mike Jordan
|
|
|
Ok for temp. ooc. All issues resolved. Noted cubicles that are receiving power and will require electrical inspection. Jeff with Layton was informed and will contact electrical contractor. I also contacted electrical division and made them aware of the situation.
|
BLD-Ceiling Grid Inspection | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | CANC |
Mike Jordan
|
|
|
customer notified that this is a FINAL inspection; Jeff Phone #: ###-####
|
FIRE-Final Inspection | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 11/1/2016 | 11/1/2016 | 11/1/2016 | P | PASS |
Mike Jordan
|
|
|
grid inspection ok. Noted that coorugated metal panels have been changed with barnwood siding, need smoke and flamespread values for interior finish. New restromm counters and lavs exceed the 34inch max height.
|
BLD-Final | 10/31/2016 | 11/1/2016 | 11/1/2016 | A | CANC |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Moved to pm inspection. Will be ceiling grid inspection. Needs fire/life/safety finals.
|
BLD-Framing/Rough-in | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | PASS |
Mike Jordan
|
|
|
Paul Phone #: ###-####. INterior steel stud framed walls and soffits ok.
|
BLD-Framing/Rough-in | 7/15/2016 | 7/18/2016 | 7/18/2016 | A | NR |
Phil Shearer
|
|
|
Quinton Phone #: ###-####. Needs electrical and plumbing rough in.
|