BLD-Final | 8/2/2017 | 8/3/2017 | 8/3/2017 | P | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 7/21/2017 | 7/21/2017 | 7/21/2017 | P | NR |
Mike Jordan
|
|
|
Rob Phone #: ###-####. Needs zoning final first.
|
FIRE-Supply Line Hydro | 7/21/2017 | 7/21/2017 | 7/21/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 7/21/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Energy code compliance | 3/30/2017 | 3/30/2017 | 3/30/2017 | P | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Framing/Rough-in | 3/30/2017 | 3/30/2017 | 3/30/2017 | P | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Energy code compliance | 3/15/2017 | 3/16/2017 | 3/16/2017 | P | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####. Roof ok.
|
BLD-Conference | 1/25/2017 | 1/27/2017 | 1/27/2017 | A | DONE |
Mike Jordan
|
|
|
Bill Phone #: ###-#### reviewed all special inspection reports to date for concrete, reinforcement, soils and geo-grid. Also discussed bolting inspection moving foward.
|
BLD-Footing | 1/13/2017 | 1/17/2017 | 1/17/2017 | A | CANC |
Mike Jordan
|
|
|
Request call ahead for access, for rebar/footings - Bill Phone #: ###-####
|
BLD-Footing | 12/14/2016 | 12/16/2016 | 12/16/2016 | A | PART |
Mike Jordan
|
|
|
rebar - Bill Phone #: ###-####. Will have special inspection. Stemwalls covered with blankets, will have supplemental heat after placement. Appears that cold weather conc. standards being followed.
|
BLD-Foundation | 12/7/2016 | 12/8/2016 | 12/8/2016 | A | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####. footings are constructed. No one no approved plans on site. Called Bill and left message. Appears that footing subgrade may be frozen.
|
BLD-Footing | 12/1/2016 | 12/5/2016 | 12/5/2016 | P | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####. Needs to resubmit plan mod for engineering on changes to foundation system. Called Bill to advise him.
|