BLD-Final | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####-please call 30 minutes prior for access. site work completed. Ok for perm occ.
|
BLD-Aging Inspection | 3/22/2017 | 3/22/2017 | 3/22/2017 | | PEND |
Mike Jordan
|
|
|
Pending completion of site work.
|
BLD-Final | 1/20/2017 | 1/20/2017 | 1/20/2017 | P | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Ok for temp occ.
|
BLD-Final | 1/19/2017 | 1/19/2017 | 1/19/2017 | P | NR |
Mike Jordan
|
|
|
Jason// please call 30min prior Phone #: ###-####
|
FIRE-Final Inspection | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/12/2017 | 1/13/2017 | 1/13/2017 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire sprinkler permit finaled and the emergency light over the east exit door repaired.
|
BLD-Other | 1/11/2017 | 1/11/2017 | 1/11/2017 | A | PEND |
Bill VanDegrift
|
|
|
just needed a phone number
|
BLD-Framing/Rough-in | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####. All previous issues have been resloved. Did discuss the need for thermal barrier over the rigid foam insulation prior to attaching the plywood at the east masonry wall.
|
BLD-Framing/Rough-in | 11/8/2016 | 11/9/2016 | 11/9/2016 | A | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. ok to dry sheet roof and cover. Needs to provide blocking on gable end truss and nail off per plan. Waiting on A44 angle to be installed per the RFI. Will also provide the truss engineering on next inspection.
|
BLD-Other | 10/26/2016 | 10/26/2016 | 10/26/2016 | P | PART |
Mike Jordan
|
|
|
jason - pouring at 3:30 Phone #: ###-####. work in progress on masonry walls 8ft. to 12ft. elevation. Will have special inspection.
|
BLD-Foundation | 10/20/2016 | 10/21/2016 | 10/21/2016 | P | PART |
Mike Jordan
|
|
|
Jason-rebar and grout-would like inspection at 1:00 Phone #: ###-####. F.F. to 4ft. elevation. Grouting in progress when on site. Special inspector on site.
|
BLD-Foundation | 10/17/2016 | 10/18/2016 | 10/18/2016 | A | PASS |
Mike Jordan
|
|
|
Rebar // Jason Phone #: ###-####. Reinforcement for interior slab on grade ok.
|
BLD-Other | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | PASS |
Phil Shearer
|
|
|
Rebar - Jason Phone #: ###-####
|
BLD-Footing | 9/12/2016 | 9/13/2016 | 9/13/2016 | P | PASS |
Mike Jordan
|
|
|
Early PM, close to 1PM please - Jason Phone #: ###-####
|