Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberBLD16-02317
StatusFinaled
Name HACKBERRY RANCH CORPORATION
Site Address 488 W PASO FINO DR
Project NameKimball Residence
Customer Number 
ePlanReviewYes
Description
WUI Zone A; **Special inspections are requird for this project, see form #310**This structure is required to be fire sprinklered in accordance with NFPA 13D.*** Permit for the construction of a new 3437 sq. ft., two story (first story 1060 sq. ft., second story 2377 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 803 sq. ft. of covered patio’s/porches and 1602 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1A/DA zoning and setbacks per planning. A separate permit is required for fire sprinklers. A deferred submittal is required for fire-rating of exterior glulams is required to be approved by Boise City building department prior to framing inspection**11/1/16 exterior Glulam in WUI Zone A exterior has been approved, see attached document//leg**. Xref GRD16-00061/ESC16-00989//leg ****A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/22/20182/23/20182/23/2018PPASS
DetailsBrandon Shaw
Scott Phone #: ###-####
DOC - Permit Finaled2/23/20182/23/20182/23/2018PPASS
DetailsBrandon Shaw
Per Home owner and Ron Johnson, Division Chief- Assistant Fire Marshal

Updated fire safety plan is approved, no sprinkler system required.
BLD-Aging Inspection1/26/20181/26/20181/26/2018 PEND
DetailsTony Young
BLD-Aging Inspection1/25/20181/25/20181/26/2018 PASS
DetailsTony Young
BLD-Energy code compliance9/11/20179/13/20179/13/2017APASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Framing/Rough-in9/11/20179/11/20179/11/2017PPASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Framing/Rough-in9/5/20179/6/20179/6/2017PPART
DetailsTony Young
Scott Phone #: ###-####,, need fire blocks, fire place rough in,, truss engineering ,, ok to insulate
BLD-Framing/Rough-in8/14/20178/15/20178/15/2017APASS
DetailsBrandon Shaw
Scott Phone #: ###-####
BLD-Wall Bracing7/24/20177/25/20177/25/2017APART
DetailsTony Young
Scott Phone #: ###-####,, exterior ok
BLD-Framing/Rough-in7/21/20177/24/20177/24/2017ANR
DetailsTony Young
Scott Phone #: ###-####,, need trades,, walk through conf only
BLD-Aging Inspection3/10/20173/10/20173/14/2017 PEND
DetailsTony Young
BLD-Aging Inspection3/9/20173/9/20173/10/2017 PEND
DetailsTony Young
BLD-Footing10/25/201610/26/201610/26/2016APART
DetailsTony Young
Scott Phone #: ###-####,, special inspection on all work,, poured,, also pending letter on continuous footing
BLD-Footing10/25/201610/25/201610/25/2016PDEFR
DetailsTony Young
Scott Phone #: ###-####
BLD-Foundation10/24/201610/25/201610/25/2016PNR
DetailsDave Hannah
Rebar // Scott Phone #: ###-####
BLD-Footing10/24/201610/25/201610/25/2016PNR
DetailsDave Hannah
Scott Phone #: ###-####
BLD-Footing10/21/201610/24/201610/24/2016ANR
DetailsMike Jordan
Scott-would like as early as possible Phone #: ###-####-please call when on way so Scott can meet. Needs 3 inches of clearance from ground, verts needs to be tied in place, lower footings to be continous and step down. Contractor to have engineer provide details for transition of ICF from lower to upper footings and for step footings.