Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberBLD16-02488
StatusIssued
Name MILLER CONSTRUCTION CORP
Site Address 521 E CAVE CT
Project Name 
Customer Number 
ePlanReviewNo
Description
*** 2-7-17 Plan Modification to use JM Corbond Spray Foam Insulation. See ESR Reports and Specification Sheets - BJM*** WUI Foothills - Zone "A" requirements. Permit for the construction of a new 4,085 sq. ft., one story single family dwelling, with a basement level (main story 2,221 sq. ft., basement level 1,864 sq. ft.) with 6 bedrooms, 4 bathrooms, approximately 249 sq. ft. of covered patio/porch and a 1001 sq. ft. attached garage per the approved plans, plan review report and any notations. Basement is proposed as unfinished. A-1 zoning and setbacks per planning.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/13/20179/13/20179/13/2017PNR
DetailsTony Young
John-please call to meet-has questions Phone #: ###-####,, needs hillside passed 1st
BLD-Aging Inspection7/7/20177/7/20177/7/2017 PASS
DetailsTony Young
BLD-Other5/10/20175/11/20175/11/2017APASS
DetailsJim Storey
John-soffit Phone #: ###-####
BLD-Conference3/9/20173/10/20173/10/2017APASS
DetailsDave Hannah
John Phone #: ###-#### ?e blocking around fireplace ok
BLD-Energy code compliance2/21/20172/22/20172/22/2017APART
DetailsDave Hannah
Insulation // John Phone #: ###-#### ok to cover but still needs to fire block fireplace contractor will do iwith sheetrock and call for inspection
BLD-Energy code compliance2/15/20172/16/20172/17/2017PPART
DetailsTony Young
Insulation // Jon Phone #: ###-####,, base layer ok
BLD-Framing/Rough-in2/3/20172/3/20172/3/2017PPASS
DetailsTony Young
john Phone #: ###-####,, still need to see base layer of foam,, also need fire stopping at top of chase of fireplace area
BLD-Framing/Rough-in1/27/20171/30/20171/30/2017AFAIL
DetailsDave Hannah
john Phone #: ###-#### c/n on site
BLD-Wall Bracing1/13/20171/17/20171/17/2017APASS
DetailsTony Young
john Phone #: ###-####
BLD-Wall Bracing1/11/20171/12/20171/12/2017AFAIL
DetailsTony Young
John Phone #: ###-####,, correction notice posted
BLD-Foundation9/6/20169/6/20169/6/2016PPART
DetailsTony Young
Wall // Pat Phone #: ###-####,, foundation grade appears low for the grade of lot, street.. ,, builder wants to pour as is,, ok at builders discretion
BLD-Footing8/26/20168/26/20168/26/2016PPASS
DetailsPhil Shearer
Pat Phone #: ###-####
BLD-Footing8/22/20168/23/20168/23/2016ANR
DetailsTony Young
Pat Phone #: ###-####,, need soils report approval