BLD-Final | 6/22/2017 | 6/22/2017 | 6/22/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner OK for Perm Occ.
|
BLD-Final | 6/19/2017 | 6/20/2017 | 6/20/2017 | A | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Final | 6/16/2017 | 6/19/2017 | 6/19/2017 | A | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Final | 6/15/2017 | 6/16/2017 | 6/16/2017 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner,, temp occupancy ok,, need trades,, zoning
|
FIRE-Final Inspection | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, in duct smoke detector is stand-alone and operational (not monitored, no other fire alarms), fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete.
|
FIRE-Conference | 6/13/2017 | 6/14/2017 | 6/14/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete
|
BLD-Ceiling Grid Inspection | 5/11/2017 | 5/12/2017 | 5/12/2017 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Energy code compliance | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Framing/Rough-in | 4/5/2017 | 4/5/2017 | 4/5/2017 | P | PASS |
Tony Young
|
|
|
Please call Jared at ###-#### 1/2 hr prior. Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Wall Bracing | 3/28/2017 | 3/29/2017 | 3/29/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Other | 3/15/2017 | 3/16/2017 | 3/16/2017 | P | PASS |
Tony Young
|
|
|
Drive through roof nailing/ structural inspect Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Concrete | 3/14/2017 | 3/14/2017 | 3/14/2017 | A | PASS |
Tony Young
|
|
|
Fence CMU and Drive Through island concrete Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Framing/Rough-in | 3/9/2017 | 3/10/2017 | 3/11/2017 | A | PART |
Tony Young
|
|
|
Main building roof nailing Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Foundation | 2/27/2017 | 2/28/2017 | 2/28/2017 | A | PASS |
Tony Young
|
|
|
Trash Enclosure Foundation walls and Fence Piers Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Foundation | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | PASS |
Tony Young
|
|
|
Drive Through Piers,Trash Enclosure footings, and fence piers/walls Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Footing | 2/21/2017 | 2/22/2017 | 2/22/2017 | A | PART |
Tony Young
|
|
|
Drive Through Footings Phone #: ###-#### Inspection requested via web by Jared Waggoner ok pending special inspection report
|
BLD-Concrete | 2/7/2017 | 2/8/2017 | 2/8/2017 | P | PEND |
Tony Young
|
|
|
Reinforced slab on grade at main building Phone #: ###-#### Inspection requested via web by Jared Waggoner,, ok pending special inspection results
|
BLD-Wall Bracing | 1/3/2017 | 1/3/2017 | 1/4/2017 | P | PART |
Tony Young
|
|
|
Please call Jared 1/2 hr before inspection ###-#### Phone #: ###-#### Inspection requested via web by Jared Waggoner,, straps from headers to walls
|
BLD-Concrete | 12/15/2016 | 12/16/2016 | 12/16/2016 | P | PART |
Tony Young
|
|
|
Please call Jared 1/2 hr prior to inspection. Reinforced slab on grade. Phone #: ###-#### Inspection requested via web by Jared Waggoner,, pending special inspection
|
BLD-Foundation | 11/17/2016 | 11/18/2016 | 11/18/2016 | P | PART |
Tony Young
|
|
|
Main Building Foundation walls, please call Jared 1/2 hr before inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner,, ok pending special inspection
|
BLD-Footing | 11/3/2016 | 11/4/2016 | 11/4/2016 | P | PART |
Tony Young
|
|
|
Last NE portion of main building and (2) interior footings Phone #: ###-#### Inspection requested via web by Jared Waggoner,, remainder of exterior footings ok
|
BLD-Footing | 11/1/2016 | 11/2/2016 | 11/2/2016 | A | PART |
Tony Young
|
|
|
Concrete is scheduled for 1pm. Phone #: ###-#### Inspection requested via web by Jared Waggoner,, 80% of main footings,, ok,, pending special inspection approval
|
FIRE-Conference | 9/23/2016 | 9/23/2016 | 9/23/2016 | A | DONE |
Katie Marron
|
|
|
Discussion with the Architect on whether a double sided monument at the corner of the intersection would suffice for building addressing on a corner lot. Based on provided site plan and site layout it should be sufficient.
|