BLD-Final | 4/6/2017 | 4/7/2017 | 4/6/2017 | A | PASS |
Jim Sly
|
|
|
Pat Phone #: ###-####-Fire permit FIR16-00659 has not had final-Pat says it has (?)
|
BLD-Final | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | NR |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
FIRE-Final Inspection | 3/24/2017 | 3/27/2017 | 3/27/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is in place. Final life fire safety inspection passed/complete.
|
BLD-Wall Bracing | 1/25/2017 | 1/26/2017 | 1/26/2017 | A | PASS |
Mike Jordan
|
|
|
pat Phone #: ###-####. 1hr. walls and electrical panels ok.
|
BLD-Other | 1/24/2017 | 1/25/2017 | 1/25/2017 | A | NR |
Jim Sly
|
|
|
Sheetrock, please call ahead - Pat Phone #: ###-#### Sheetrock membrane at rated walls not complete.
|
BLD-Energy code compliance | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 1/18/2017 | 1/18/2017 | 1/18/2017 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Energy code compliance | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Needs to complete roll blocking and box out electrical panels.
|
BLD-Framing/Rough-in | 1/12/2017 | 1/12/2017 | 1/12/2017 | A | FAIL |
Mike Jordan
|
|
|
Fireblock all concealed areas at 1st. floor ceiling. Complete airseal, roll block all cantilevered floor joist, provide truss engineering, Box out the elctrical service panels with 2 layers of 5/8 type x rock. ok to insualte. Corection notice issued.
|
BLD-Framing/Rough-in | 12/20/2016 | 12/21/2016 | 12/21/2016 | A | DEFR |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Due to the type of plan modification, plan mod will need to resubmitted to plan review for approval.
|
BLD-Framing/Rough-in | 12/16/2016 | 12/19/2016 | 12/19/2016 | A | NR |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Could not locate approved plans on site, Also contractor needs to provide staple conversion from engineer of record.
|
BLD-Framing/Rough-in | 12/14/2016 | 12/14/2016 | 12/14/2016 | P | NR |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | CANC |
Mike Jordan
|
|
|
pat Phone #: ###-####
|
BLD-Conference | 12/14/2016 | 12/14/2016 | 12/14/2016 | A | DONE |
Mike Jordan
|
|
|
pat Phone #: ###-####
|
BLD-Framing/Rough-in | 12/12/2016 | 12/12/2016 | 12/12/2016 | P | FAIL |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Needs to install all exterior straps as shown on plan. Noted several areas were sheathing is not nailed. Noted several items that are not built as per the approved plan. Work needs to be as per approved plan or engineer of record to sign of on structure. Also noted 1hr. fire partitions not per plan. Construct the 1hr. fire partition per plan or have architect provide alternate detail to building official for approval.
|
BLD-Foundation | 10/4/2016 | 10/5/2016 | 10/5/2016 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 10/3/2016 | 10/4/2016 | 10/4/2016 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|