BLD-Final | 12/21/2016 | 12/21/2016 | 12/21/2016 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 12/20/2016 | 12/21/2016 | 12/21/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per Carl updated plans showing the office in the warehouse is not required and only one exit is required from the warehouse. Also the owner elected to remove the storage racking in leu of getting a racking permit.
|
FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/20/2016 | A | CANC |
Troy Cobbley
|
|
|
Ben Phone #: ###-####
|
BLD-Final | 12/19/2016 | 12/20/2016 | 12/20/2016 | P | CANC |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/19/2016 | A | FAIL |
Troy Cobbley
|
|
|
Inspection turned into a conference with the contractor. We went over door hardware issues and lack of notes. Missing duct smoke detector and tags on fire extinguishers. Dan Phone #: ###-####
|
BLD-Framing/Rough-in | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####. Roof framing and roof sheathing ok. New opening in existing building ok.
|
BLD-Foundation | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PART |
Mike Jordan
|
|
|
Dan Phone #: ###-####. work in progress on masonry walls F.F. to 4ft. elevation. Will have special inspection.
|
BLD-Foundation | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Mike Jordan
|
|
|
rebar, 10:30am pour; Randy Phone #: ###-####. Work in progress. Will hace special inspection.
|
BLD-Foundation | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | CANC |
Mike Jordan
|
|
|
Dan-rebar Phone #: ###-####
|
BLD-Footing | 10/20/2016 | 10/20/2016 | 10/20/2016 | A | PART |
Mike Jordan
|
|
|
Dan-rebar Phone #: ###-####. Work in progress. Ok after special inspection has passed.
|