BLD-Final | 12/30/2016 | 12/30/2016 | 12/30/2016 | P | PASS |
Jim Sly
|
|
|
Larry Phone #: ###-####
|
FIRE-Final Inspection | 12/30/2016 | 12/30/2016 | 12/30/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 12/19/2016 | 12/19/2016 | 12/19/2016 | P | PART |
Troy Cobbley
|
|
|
Gate posts are in but gates have not been installed yet. Plans have been approved with the new fencing/gates. Will be ok to final when gate/width can be verified.
|
BLD-Final | 12/15/2016 | 12/16/2016 | 12/16/2016 | P | PART |
Mike Jordan
|
|
|
Larry Phone #: ###-####. Ok for temp occ. Need final letter from special inspection agency.
|
FIRE-Final Inspection | 12/15/2016 | 12/16/2016 | 12/16/2016 | A | PART |
Troy Cobbley
|
|
|
A 30 day temporary is being given with Scott's permission until the as-builts showing the new fences and gates have approved, and the fences and gates installed/verified.
|
FIRE-Final Inspection | 12/14/2016 | 12/15/2016 | 12/15/2016 | P | FAIL |
Troy Cobbley
|
|
|
Provide as-builts to plan review showing the new fences and gates. The vehicle gate to be 20' min. clearance and the a new man gate to be provided at the west side fence. Provide fire dept access/fire lane signage at both property entrances as discussed. All other items ok. As per plan review the knox key at the west property entry and narrow width has been approved by the fire dept.
|
FIRE-Conference | 12/13/2016 | 12/13/2016 | 12/13/2016 | P | DONE |
Katie Marron
|
|
|
Phone discussion with contractor on sequence of inspections in regards to knox box/switches being installed on all electric gates. Discussed that he should coordinate with fire department for key hand over/ops check. Fire department is not required at final life safety inspection.
|
FIRE-Conference | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | DONE |
Katie Marron
|
|
|
Discussed with architect on address number placement. Directed that if building numbers were not visible from the street than additional signage at the street/gate would be required.
|
BLD-Foundation | 11/3/2016 | 11/4/2016 | 11/4/2016 | P | PART |
Mike Jordan
|
|
|
As late as possible // Larry Phone #: ###-####. Work in progress. Will have special inspection.
|
FIRE-Conference | 11/4/2016 | 11/4/2016 | 11/4/2016 | P | DONE |
Katie Marron
|
|
|
Survey miss measured front gate width it is 16' and not the agreed with 19'. Approved access is now from the drive to the south and around back. If front gate is electric it shall have a knox switch still, to provide options as needed. Inspector to verify access is marked/signed.
|
BLD-Foundation | 10/24/2016 | 10/25/2016 | 10/25/2016 | P | PART |
Mike Jordan
|
|
|
Wall pour is Wednesday 830am // Larry Phone #: ###-####. Work in progress, loading dock wall. Will have special inspection.
|
BLD-Footing | 10/18/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Mike Jordan
|
|
|
pouring 11:30 - Larry Phone #: ###-####. Perimeter footings, work in progress. OK to place after special inspection has passed.
|