Information based on query as of Wednesday, June 19, 2024.
Permit Information
Permit NumberBLD16-02809
StatusFinaled
Name STEVE HART CONSTRUCTION
Site Address 2710 W SUNRISE RIM RD Unit: 100
Project NameL. S. Idaho - Suite #100
Customer Number 
ePlanReviewYes
Description
(L. S. IDAHO – 1st FLOOR SUITE #100) Permit is to remodel existing 3,110 sq. ft. office space on the first floor. This permit is approved contingent upon adhering to the approved plans on file. Work to include: removal of select door/door frames, removal of select interior nonbearing walls, removal of select millwork, construction of select interior non-bearing walls to create (3) offices, a conference room, a waiting area, a server room and an open office area, new light fixtures, electrical work, mechanical work and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection1/12/20181/12/20181/12/2018 PASS
DetailsJim Storey
Ok for perm occ.450
DOC - Permit Finaled1/12/20181/12/20181/12/2018PPASS
DetailsJim Storey
Ok for perm occ.450
FIRE-Final Inspection8/31/20178/31/20178/31/2017PCANC
DetailsTroy Cobbley
FIRE-Final Inspection8/31/20178/31/20178/31/2017PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Conference8/31/20178/31/20178/31/2017PPASS
DetailsMike Jordan
Steve Phone #: ###-####. Ok for perm occ.
BLD-Final9/30/20169/30/20169/30/2016PPART
DetailsMike Jordan
Steve-would like as late as possible-fire to be done early PM Phone #: ###-####. Ok for temp occ. Needs correct door hardware.
FIRE-Final Inspection9/29/20169/30/20169/30/2016APART
DetailsTroy Cobbley
A temporary occupancy is being give for fire life safety until the fire alarm pemit is finaled and the correct hardware is provided on all doors as discussed.
FIRE-Conference9/6/20169/6/20169/6/2016PDONE
DetailsTroy Cobbley
I spoke to the general contractor about the need for a fire alarm permit to provide modifications to the existing system for new wall layout.