BLD-Final | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 3/14/2017 | 3/14/2017 | 3/14/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 3/6/2017 | 3/7/2017 | 3/7/2017 | A | PART |
Troy Cobbley
|
|
|
A temporary is being given with the Boise Fire Dept. permission until the fire alarm permit has been finaled (need approved as-builts), and the correction items for the fire dept have been addressed which include the remaining sign at the remote emergency off switch, 6" curbing and the fuel pumps repaired.
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Final | 3/6/2017 | 3/7/2017 | 3/7/2017 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer. Ok for temp occ. Will be ok for perm occ. once fire/life/safety signs perm. and the fire alarm signs perm.
|
FIRE-Final Inspection | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for a final yet, I went over requirements with Chris such as needing the project related fire alarm permit addressed, remove the deadbolt on the beer cooler, need fire extinguisher for store, need verification of permiting through Fire Dept,, need verification Fire Dept is ok with the pumps/tanks and lack of 6" at the gas pumps, testing of the emergency off buttons, missing exit discharge lights....ect
|
BLD-Energy code compliance | 1/27/2017 | 1/27/2017 | 1/27/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 1/26/2017 | 1/27/2017 | 1/27/2017 | A | NR |
Mike Jordan
|
|
|
Wall insulation inspection. Late morning inspection, if at all possible. Thanks, Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 1/25/2017 | 1/26/2017 | 1/26/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer. Interior steel stud framed walls, furred walls and hardlids ok.
|
BLD-Footing | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | DEFR |
Mike Jordan
|
|
|
Grout at 9:15, Masonry rebar - Chris Phone #: ###-####. Special inspection.
|
BLD-Other | 11/30/2016 | 12/1/2016 | 12/1/2016 | P | CANC |
Mike Jordan
|
|
|
Masonry rebar & re-grout, grouting at 1:45 - Chris Phone #: ###-####
|
BLD-Other | 11/29/2016 | 11/30/2016 | 11/30/2016 | A | DEFR |
Mike Jordan
|
|
|
masonry grout at 8:30AM - Chris Phone #: ###-####.
|
BLD-Other | 11/23/2016 | 11/28/2016 | 11/28/2016 | A | PART |
Mike Jordan
|
|
|
masonary grout & rebar, scheduled for 1:15PM - Chris Phone #: ###-####. Work in progress, masonry exterior walls, FF to 4ft. elevation. Will have special inspection.
|
BLD-Other | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Mike Jordan
|
|
|
Rebar - Chris Phone #: ###-####. Column pad footings for fuel canopy.
|
BLD-Foundation | 11/8/2016 | 11/9/2016 | 11/9/2016 | A | PART |
Mike Jordan
|
|
|
Stem wall pour at the C-Store. Concrete is scheduled for 9AM. Please call me with any questions. Thanks, Phone #: ###-#### Inspection requested via web by Chris Palmer. Work in progress, will have special inspection. Needs clean debrie from bottom of stemwall.
|
BLD-Footing | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | PART |
Mike Jordan
|
|
|
Perimeter footings for store portion. Work in progress. Will have special inspection.
|
BLD-Footing | 11/1/2016 | 11/2/2016 | 11/2/2016 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Justin Parrish
|