BLD-Ceiling Grid Inspection | 2/9/2018 | 2/9/2018 | 2/9/2018 | P | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####. OK for perm occ.
|
BLD-Final | 2/9/2018 | 2/9/2018 | 2/9/2018 | P | PASS |
Mike Jordan
|
|
|
Ceiling grid insp on 2/9/18 was supposed to be final bldg insp. see inspectors notes in ceiling grid inspection for OK for perm occupancy
|
BLD-Final | 1/18/2018 | 1/22/2018 | 1/22/2018 | P | PEND |
Mike Jordan
|
|
|
Adam Phone #: ###-####-no plan on site but will try and get them from the architect. Will need to architect to submit plan modifiaction to show the additional two offices that have been constructed.
|
FIRE-Final Inspection | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
Adam Phone #: ###-####
|
FIRE-Conference | 6/7/2017 | 6/12/2017 | 6/12/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete, fire alarm modifications still need to be made to the existing system, fire sprinkler modifications have been completed, fire extinguishers are in place with current inspection tags, exit signs with discharge lighting will be installed before final inspection, exterior exits that are designated as emergency exits will also need to have exit discharge illumination installed per note number 12 on fire plan review comments.
|
FIRE-Final Inspection | 3/6/2017 | 3/6/2017 | 3/6/2017 | P | FAIL |
Troy Cobbley
|
|
|
No plans or small documents on site. I did a courtesy walk through with Adam. I noted the need for fire sprinkler and fire alarm modifications in several locations. It appears the emergency generator has been removed so backup power for emergency lights is an issue. Door hardware does not meet ADA on the new doors.
Leanne Phone #: ###-####
|