BLD-Final | 7/18/2018 | 7/18/2018 | 7/19/2018 | P | PASS |
Tony Young
|
|
|
need pass final for perm occ (not sure if you need to go out or not?) Steve Ellis Phone #: ###-####
|
BLD-Aging Inspection | 7/2/2018 | 7/2/2018 | 7/5/2018 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/30/2018 | 4/30/2018 | 5/1/2018 | | PASS |
Tony Young
|
|
|
|
BLD-Final | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | PART |
Tony Young
|
|
|
Steve Phone #: ###-####,, ok pending others
|
BLD-Final | 2/28/2018 | 3/1/2018 | 3/1/2018 | P | PART |
Tony Young
|
|
|
still need GRD permit finaled as well as ELE Steve Phone #: ###-####,, temp. occupancy ok
|
FIRE-Final Inspection | 2/28/2018 | 3/1/2018 | 3/1/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Steve Phone #: ###-####
|
FIRE-Final Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire sprinkler underground and overhead permits finaled. Need the project related fire alarm permit finaled. A stand alone smoke alarm is being required to be added in the Infant room as per the Assistant Fire Marshal. A separate permit is needed for the second business located in this building. Deadbolts need to be removed. Approved hardware is needed on the Restroom Barn Doors. Fire extinguishers need to be mounted. Exit signs and emergency lights need to be tested. Small documents need to be on site. An address needs to be installed as discussed.
Steve-please call 10 minutes prior to meet-wants to go threw inspection with him Phone #: ###-####
|
FIRE-Conference | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | DONE |
Jim Page
|
|
|
Fire conference complete. Provide panic hardware on southwest exterior gate. Provide knox box by main entry. Verify door hardware is code compliant on level 2 balcony door. provide fire extinguishers throughout building. Provide correct size for address numbering.
|
BLD-Energy code compliance | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Tony Young
|
|
|
Steve Phone #: ###-####
|
BLD-Energy code compliance | 12/15/2017 | 12/15/2017 | 12/18/2017 | P | PART |
Dave Hannah
|
|
|
Steve Phone #: ###-#### front office area and back two class rooms ok to cover
|
BLD-Framing/Rough-in | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | PASS |
Dave Hannah
|
|
|
final framing and energy seal // Steve Ellis Phone #: ###-#### ok to insulate
|
BLD-Framing/Rough-in | 12/7/2017 | 12/7/2017 | 12/7/2017 | P | CANC |
Dave Hannah
|
|
|
.
|
BLD-Framing/Rough-in | 12/7/2017 | 12/7/2017 | 12/7/2017 | P | PEND |
Dave Hannah
|
|
|
needs air seal package installed needs fire blocking int shear finised do not insulate framing is ok
|
BLD-Framing/Rough-in | 11/20/2017 | 11/20/2017 | 11/22/2017 | P | PART |
Dave Hannah
|
|
|
call 1 hr prior // framing/conference // Victor Phone #: ###-#### ok to cover shear wall at stairs
|
BLD-Wall Bracing | 9/20/2017 | 9/21/2017 | 9/21/2017 | P | PASS |
Tony Young
|
|
|
Shear // Victor Phone #: ###-####
|
BLD-Wall Bracing | 9/19/2017 | 9/20/2017 | 9/20/2017 | P | PART |
Tony Young
|
|
|
Shear // Victor Phone #: ###-####,, work in progress,, ok
|
BLD-Wall Bracing | 9/19/2017 | 9/19/2017 | 9/19/2017 | P | PART |
Tony Young
|
|
|
Victor Phone #: ###-####,, work in progress, ok so far
|
BLD-Wall Bracing | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | PART |
Tony Young
|
|
|
Victor Phone #: ###-####,, work in progress
|
BLD-Wall Bracing | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PART |
Tony Young
|
|
|
Victor Phone #: ###-####,, on site conf,, work in progress east side,, ok so far
|
BLD-Wall cover | 9/15/2017 | 9/15/2017 | 9/15/2017 | P | NR |
Tony Young
|
|
|
Victor Phone #: ###-####,, walk around part,, needs too much,, re-nail and re-call
|
BLD-Framing/Rough-in | 9/15/2017 | 9/15/2017 | 9/15/2017 | P | NR |
Tony Young
|
|
|
Victor Phone #: ###-####
|
BLD-Wall Bracing | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | CANC |
Jim Sly
|
|
|
left off piece of shear to see fire wall blocking // Victor Phone #: ###-####
|
BLD-Framing/Rough-in | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PART |
Jim Sly
|
|
|
left off piece of shear to see fire wall blocking // Victor Phone #: ###-#### Verified fireblocking in place........OK to cover 2nd story Mechanical area.......Both sides of walls.
|
BLD-Aging Inspection | 7/13/2017 | 7/13/2017 | 7/14/2017 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 7/12/2017 | 7/12/2017 | 7/12/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Foundation | 2/27/2017 | 2/28/2017 | 2/28/2017 | A | PASS |
Tony Young
|
|
|
Mark-rebar-trash enclosure Phone #: ###-####,, also verified stem wall insulation,, and pier for south entry canopy
|
BLD-Foundation | 12/19/2016 | 12/20/2016 | 12/20/2016 | A | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, special inspector on site.. ok,, pending final report
|
BLD-Footing | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, ok pending special inspection
|