BLD-Final | 9/28/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Jim Storey
|
|
|
Please call when you are nearby. I will be just around the corner. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen
|
DOC - Permit Finaled | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Jim Page
|
|
|
Previously noted items have been completed, final life fire safety inspection complete.
Phone #: ###-#### Inspection requested via web by Mark Steen
|
FIRE-Final Inspection | 9/21/2018 | 9/24/2018 | 9/24/2018 | A | FAIL |
Troy Cobbley
|
|
|
Provide small documents, provide fire extin\guishers for mezzanine as discussed, provide electrical room signage, provide panic hardware for electrical room and provide final inspection for the project related fire alarm permit.
|
BLD-Wall cover | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Jim Storey
|
|
|
Elevator shaftwall framing ; cover inspection. Phone #: ###-#### Inspection requested via web by Mark Steen
|
BLD-Concrete | 5/4/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Jim Storey
|
|
|
100 yard deck pour 5amTuesday with MTI attending. Note: A separate steel framing inspection request is already set up for the same time as this inspection. (Saves two trips) Thanks Phone #: ###-#### Inspection requested via web by Mark Steen
|
BLD-Framing/Rough-in | 5/4/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Jim Storey
|
|
|
MTI welding Insp due to complete partial approval noon Monday. A concrete inspection will be requested for the same time as this framing inspection occurs. Concrete for elevated deck delivers Tuesday at 5am with MTI attending. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen
|
BLD-Concrete | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Jim Storey
|
|
|
Pour back SOG ; two small added footings. Also, exterior stair foundations. MTI will be inspecting steel and mud tomorrow. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen si report pending
|
BLD-Footing | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | PART |
Jim Storey
|
|
|
MTI due on site Friday at 1:30pm, Concrete due at 2pm. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen si on site
|
BLD-Foundation | 3/16/2018 | 3/19/2018 | 3/19/2018 | A | PASS |
Jim Storey
|
|
|
MTI to Insp rebar at 11am, 5 yds delivered at 11:30am for elev pit walls Phone #: ###-#### Inspection requested via web by Mark Steen
|
BLD-Footing | 3/12/2018 | 3/13/2018 | 3/13/2018 | P | PASS |
Brandon Shaw
|
|
|
Elevator pit footing Phone #: ###-#### Inspection requested via web by Mark Steen
|