Permit Information
Permit NumberBLD16-03095
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 2505 S FEDERAL WAY
Project NameVanilla 2nd Floor
Customer Number 
ePlanReviewYes
Description
**(VANILLA – 2nd FLOOR)** //Plan modification to alter stair width, change the 1st floor lobby layout, added a door at 1st floor lobby, relocate the elevator, relocate the elevator roof penthouse and remove opening on the second floor to add approx. 108 sq. ft. to the second floor. 2-15-2018 JG// NO OCCUPANCY ALLOWED UNDER THIS PERMIT. TENANT SHALL APPLY FOR CERTIFICATE OF OCCUPANCY PRIOR TO OCCUPYING THE SPACE. Permit is to remodel an existing 14,153 sq. ft. building by adding 8,310 sq. ft. second floor. Approval is contingent upon adhering to the approved plans on file. Work to include: new 5’ wide concrete walkway from rear exterior exit landing to the existing sidewalk, new engineered upper second floor decking, construction of select interior nonbearing walls to create a lobby area, an elevator shaft and stairway walls, new interior elevator, new interior exit stairway, new exterior exit stairway, new exterior door opening, new elevator, new light fixtures, electrical work and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. Note: Minimum number of required plumbing fixture and area of refuge to be addressed when future new tenant occupies the second floor, see attached document in Tidemark. JG
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/28/201810/1/201810/1/2018PPASS
DetailsJim Storey
Please call when you are nearby. I will be just around the corner.
Thanks Phone #: ###-#### Inspection requested via web by Mark Steen
DOC - Permit Finaled10/1/201810/1/201810/1/2018PPASS
DetailsJim Storey
FIRE-Final Inspection9/27/20189/28/20189/28/2018APASS
DetailsJim Page
Previously noted items have been completed, final life fire safety inspection complete.

Phone #: ###-#### Inspection requested via web by Mark Steen
FIRE-Final Inspection9/21/20189/24/20189/24/2018AFAIL
DetailsTroy Cobbley
Provide small documents, provide fire extin\guishers for mezzanine as discussed, provide electrical room signage, provide panic hardware for electrical room and provide final inspection for the project related fire alarm permit.
BLD-Wall cover5/29/20185/30/20185/30/2018APASS
DetailsJim Storey
Elevator shaftwall framing ; cover inspection. Phone #: ###-#### Inspection requested via web by Mark Steen
BLD-Concrete5/4/20185/7/20185/7/2018PPASS
DetailsJim Storey
100 yard deck pour 5amTuesday with MTI attending. Note: A separate steel framing inspection request is already set up for the same time as this inspection. (Saves two trips) Thanks Phone #: ###-#### Inspection requested via web by Mark Steen
BLD-Framing/Rough-in5/4/20185/7/20185/7/2018PPASS
DetailsJim Storey
MTI welding Insp due to complete partial approval noon Monday. A concrete inspection will be requested for the same time as this framing inspection occurs. Concrete for elevated deck delivers Tuesday at 5am with MTI attending. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen
BLD-Concrete4/11/20184/11/20184/11/2018PPASS
DetailsJim Storey
Pour back SOG ; two small added footings. Also, exterior stair foundations. MTI will be inspecting steel and mud tomorrow. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen si report pending
BLD-Footing4/5/20184/6/20184/6/2018PPART
DetailsJim Storey
MTI due on site Friday at 1:30pm, Concrete due at 2pm. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen si on site
BLD-Foundation3/16/20183/19/20183/19/2018APASS
DetailsJim Storey
MTI to Insp rebar at 11am, 5 yds delivered at 11:30am for elev pit walls Phone #: ###-#### Inspection requested via web by Mark Steen
BLD-Footing3/12/20183/13/20183/13/2018PPASS
DetailsBrandon Shaw
Elevator pit footing Phone #: ###-#### Inspection requested via web by Mark Steen