BLD-Final | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PASS |
Mike Jordan
|
|
|
All issues resolved. Ok for perm occ.
|
BLD-Final | 2/8/2017 | 2/9/2017 | 2/9/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. vertical grab bar not with in the 39 to 41 inch tolerance. Remove door hardware from inactive leaf of double doors.
|
FIRE-Final Inspection | 2/7/2017 | 2/8/2017 | 2/8/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. The appliances under the kitchen hood have not installed yet and therefore the project related hood suppression permit is not being inspected/finaled. The general contractor has been notified that the appliances/hood are not to be used until inspected/tested. There is a separate FIR for the suppression system that is not being finaled until work is complete that is not attached to this BLD permit.
|
FIRE-Final Inspection | 2/6/2017 | 2/7/2017 | 2/7/2017 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for final yet. I did verify the fire extinguishers, door hardware and the exit signs/emergency lighting. Need the fire alarm and hood suppression permits/inspections prior to a building life safety sign off.
|
BLD-Conference | 2/3/2017 | 2/3/2017 | 2/3/2017 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Conference | 2/2/2017 | 2/3/2017 | 2/3/2017 | A | CANC |
Mike Jordan
|
|
|
conference for Building and Safety Final Phone #: ###-#### Inspection requested via web by Todd Landvatter. Moved to pm.
|
BLD-Ceiling Grid Inspection | 1/31/2017 | 1/31/2017 | 1/31/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Ceiling Grid Inspection | 1/28/2017 | 1/30/2017 | 1/30/2017 | A | PASS |
Mike Jordan
|
|
|
Remaining 2nd floor, main lab and incubators 1st floor. Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Ceiling Grid Inspection | 1/23/2017 | 1/24/2017 | 1/24/2017 | P | PART |
Jim Sly
|
|
|
2nd floor Phone #: ###-#### Inspection requested via web by Todd Landvatter Grid Ceiling OK except.....Halls, Storage, Electr, and Lab.
|
BLD-Ceiling Grid Inspection | 1/19/2017 | 1/20/2017 | 1/20/2017 | P | PASS |
Mike Jordan
|
|
|
partial, downstairs. Phone #: ###-#### Inspection requested via web by Todd Landvatter. 1st. floor under mezz ok for tile.
|
BLD-Wall cover | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Mike Jordan
|
|
|
Fire calking elevator equipment room Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Framing/Rough-in | 11/23/2016 | 11/28/2016 | 11/28/2016 | A | PASS |
Mike Jordan
|
|
|
2nd floor framing. Elevator equipment room fire calking 1hr rating. Phone #: ###-#### Inspection requested via web by Todd Landvatter. 2nd. floor interior steel stud walls ok.
|
BLD-Framing/Rough-in | 11/19/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Mike Jordan
|
|
|
rough framing south phase ground floor, and review stamped letter for 24 in OC framing in lieu of 16 in OC. Phone #: ###-#### Inspection requested via web by Todd Landvatter. North half framing, 1st. floor ok per letter from architect approving stud spacing at 14 inches o.c. South half framing, 1st floor ok, pending electrical and plumbing rough in inspections.
|
BLD-Framing/Rough-in | 11/17/2016 | 11/17/2016 | 11/17/2016 | P | FAIL |
Dave Hannah
|
|
|
under mezzanine Phone #: ###-#### Inspection requested via web by Todd Landvatter plans call for 16 oc spacing framed at 24 oc
|
BLD-Conference | 11/15/2016 | 11/15/2016 | 11/15/2016 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Discussed phased inspections for framing and UL listings for 1hr. room.
|
BLD-Framing/Rough-in | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | DEFR |
Mike Jordan
|
|
|
Steel Mezzanine deck reinforcing and welding before concrete. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Will have special inspection.
|
BLD-Concrete | 10/26/2016 | 10/27/2016 | 10/27/2016 | A | DEFR |
Mike Jordan
|
|
|
final lift grout elevator 11am. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Special inspector on site. Grout placement completed when arrived on site.
|
BLD-Concrete | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | PART |
Mike Jordan
|
|
|
3rd grout lift elevator shaft at 11am. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Work in progress on elevator shaft, 16ft. elevation to 24ft. Will have special inspection. inspection.
|
BLD-Concrete | 10/24/2016 | 10/25/2016 | 10/25/2016 | A | PART |
Mike Jordan
|
|
|
second 8 foot grout lift @ 11am. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Work in progress for elevator shaft, 8ft. to 16ft. elevation, special inspector will be on site.
|
BLD-Concrete | 10/21/2016 | 10/24/2016 | 10/24/2016 | A | PART |
Mike Jordan
|
|
|
CMU grout 11 AM Phone #: ###-#### Inspection requested via web by Todd Landvatter. Work in progress on masonry elevator shaft, F.F. to 8ft. elevation, hight lift grout with cleanouts. Verified Letter from engineer of record approving high lift grouting.
|
BLD-Footing | 10/18/2016 | 10/19/2016 | 10/19/2016 | A | DEFR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Concrete placed when arrived on site. reinforcement was inspected by special inspection.
|
BLD-Wall Bracing | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | PART |
Mike Jordan
|
|
|
rebar CMU Elevator shaft Phone #: ###-#### Inspection requested via web by Todd Landvatter. Elevator pit to finish floor. Work in progress, needs to place vert. reinforcement. Will have special inspection.
|
BLD-Footing | 10/10/2016 | 10/11/2016 | 10/11/2016 | A | PASS |
Mike Jordan
|
|
|
late morning inspection for 1pm pour. Phone #: ###-#### Inspection requested via web by Todd Landvatter. F1 type column pad footings for new stairs ok. Work in progress on elevator pit reinforcing. ok t o place concrete after special inspection signs off.
|