Permit Information
Permit NumberBLD16-03292
StatusFinaled
Name OKLAND CONSTRUCTION CO INC
Site Address 1101 W FRONT ST
Project NameParcel B Parking Garage
Customer Number 
ePlanReviewYes
Description
(PARCEL B PARKING GARAGE) **PROJECT MANAGEMENT - Angie Brosious** **PLAN MODIFICATION 3 TO ADD AN ADDITIONAL TIER TO THE STRUCTURE. Stand pipe fire protection shall be extended to this additional level. Separate fire protection permits are requried.** PLAN MODIFICATION #2 FOR BELOW SLAB PLUMBING AND ELECTRICAL CONDUITS."" ""MODIFICATION CHANGING THE INTERIOR SLOPE OF THE GARAGE FLOOR AND INTERIOR DRAINAGE PLUMBING"" Permit for the construction of a 228,548 sq. ft., 4 tier parking garage including 13,392 sq. ft. of office area on the first story to be type IB construction with work to in garage construction and general site grading and utilities per the approved plans and any notations. The office requires a separate permit for the tenant improvement and occupancy of this area. This building is to be fully fire sprinklered per NFPA 13. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/11/20189/12/20189/12/2018PPASS
DetailsDave Hannah
Jeff Phone #: ###-####
FIRE-Final Inspection7/23/20187/24/20187/24/2018APASS
DetailsJim Page
Final life fire safety inspection complete.

Jeff Phone #: ###-####
BLD-Aging Inspection7/16/20187/16/20187/18/2018 PEND
DetailsDave Hannah
BLD-Aging Inspection4/18/20184/18/20184/24/2018 PEND
DetailsDave Hannah
BLD-Final2/5/20182/5/20182/6/2018PPEND
DetailsDave Hannah
JEFF - DAVE DID WALKTHRU ON FRI - WANTS TO COME BACK TO CHECK STAIRWELLS Phone #: ###-#### ok for temp occ stir towers cleaned up
BLD-Final1/31/20182/1/20182/1/2018APART
DetailsDave Hannah
Late morning after life/safety - Levels 2-5 TCO approval - Jeff Phone #: ###-#### ok for TCO
FIRE-Final Inspection1/31/20182/1/20182/1/2018APART
DetailsJim Page
Previously noted items have been addressed, temp signs are in place for fire alarm control panel, fire sprinkler riser room and FDC/Standpipe details. Temp fill has been put in place for stairwell door windows. Life fire safety inspection for TCO request complete. Stairwells are not to be used as storage after this inspection.
FIRE-Final Inspection1/30/20181/31/20181/31/2018AFAIL
DetailsJim Page
Emergency lighting that did not operate needs to be repaired and retested. Signage needs to be installed on the fire panel control room, the fire sprinkler riser room as well as signage for the dry standpipe with dry standpipe info mounted by the FDC location. Mount fire extinguishers in discussed locations and provide inspection tags for each fire extinguisher. Remove storage/combustible material from stairwells. Install glass in stairwell doors.
BLD-Final1/26/20181/29/20181/31/2018PPEND
DetailsDave Hannah
levels 2-5 - jeff Phone #: ###-####
BLD-Final1/30/20181/31/20181/31/2018PCANC
DetailsDave Hannah
Jeff Phone #: ###-####
FIRE-Final Inspection1/30/20181/31/20181/31/2018PDONE
DetailsJim Page
levels 2-5- later afternoon- Jeff Phone #: ###-####
BLD-Final1/16/20181/17/20181/17/2018ADONE
DetailsDave Hannah
TCO - Robert Phone #: ###-####
BLD-Final1/11/20181/16/20181/17/2018PPART
DetailsDave Hannah
Robert Phone #: ###-####phase 1 ground floor only ok
FIRE-Final Inspection1/11/20181/16/20181/16/2018APART
DetailsJim Page
Partial final inspection complete for level 1 parking, ry standpipe inspection complete for levels 1, 2 and 3, fire alarm inspection complete for level 1, fire extinguishers are in place for level 1, permit will remain in issued status until completion of project.
BLD-Framing/Rough-in1/5/20181/8/20181/8/2018PPEND
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Framing/Rough-in11/29/201711/30/201712/5/2017APASS
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Conference10/26/201710/26/201710/27/2017PDONE
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Other10/16/201710/18/201710/24/2017APART
DetailsDave Hannah
rebar // Robert Phone #: ###-#### ok met with al from mti
BLD-Foundation8/16/20178/17/20178/18/2017APEND
DetailsDave Hannah
Rebar // Robert Phone #: ###-####
BLD-Foundation4/25/20174/26/20175/4/2017APASS
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Foundation4/17/20174/19/20174/21/2017APEND
DetailsDave Hannah
Robert-rebar Phone #: ###-#### signed off by spec inspection
BLD-Foundation4/3/20174/4/20174/4/2017APASS
DetailsDave Hannah
Rebar // Robert Phone #: ###-####
BLD-Foundation3/28/20173/30/20173/30/2017APEND
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Foundation3/23/20173/29/20173/30/2017APEND
DetailsDave Hannah
Rebar // Robert Phone #: ###-#### ok after spec inspection sign off
BLD-Foundation3/16/20173/17/20173/17/2017APASS
DetailsDave Hannah
Rebar // Rob Phone #: ###-####
BLD-Foundation2/16/20172/17/20172/17/2017APART
DetailsJim Storey
Rebar // Robert Phone #: ###-#### placed w/si