BLD-Final | 8/11/2017 | 8/14/2017 | 8/14/2017 | A | PASS |
Mike Jordan
|
|
|
Harvey Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 8/9/2017 | 8/10/2017 | 8/10/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide single action hardware on doors with locks prior to a building inspection.
|
BLD-Final | 8/9/2017 | 8/9/2017 | 8/9/2017 | P | NR |
Mike Jordan
|
|
|
harvey Phone #: ###-#### - call for access code. Needs fire/life/safety fianl first.
|
BLD-Ceiling Grid Inspection | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Mike Jordan
|
|
|
Harvey Phone #: ###-####. Base layer 5/8 type x rock ok on 1hr. roof/ceiling assembly.
|
BLD-Energy code compliance | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | PASS |
Mike Jordan
|
|
|
Insulation // Harvey Phone #: ###-####
|
BLD-Wall cover | 4/14/2017 | 4/17/2017 | 4/17/2017 | P | PASS |
Mike Jordan
|
|
|
Joseph Phone #: ###-####. All issues resolved. ok to insulate.
|
BLD-Conference | 4/13/2017 | 4/14/2017 | 4/14/2017 | A | DONE |
Mike Jordan
|
|
|
Joseph Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | PART |
Mike Jordan
|
|
|
Joseph Phone #: ###-####. firecaulk all penetrations through top plate. Needs to remove foam from can light enclosures and use firecaulk. Will recall when complete and wil meet contractor to go over remainder.
|
BLD-Framing/Rough-in | 2/17/2017 | 2/17/2017 | 2/17/2017 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Have framing and Firestopping issues......but let insulate for now.
|
BLD-Framing/Rough-in | 1/10/2017 | 1/11/2017 | 1/10/2017 | P | NR |
Mike Jordan
|
|
|
Joseph Phone #: ###-####. Needs MEP rough in inspections first.
|