BLD-Final | 5/9/2017 | 5/10/2017 | 5/10/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
DOC - Permit Finaled | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/14/2017 | 4/14/2017 | 4/19/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/13/2017 | 4/13/2017 | 4/19/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 11/29/2016 | 11/30/2016 | 11/30/2016 | A | PASS |
Phil Shearer
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 11/23/2016 | 11/25/2016 | 11/25/2016 | A | PART |
Phil Shearer
|
|
|
would like call ahead; larry Phone #: ###-####. Point load support for beam at the bottom of the stairs, Air seal, Straps for the potal frame. OK to insulate
|
BLD-Other | 11/15/2016 | 11/15/2016 | 11/15/2016 | P | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####,, WUI soffit
|
BLD-Wall Bracing | 11/14/2016 | 11/15/2016 | 11/15/2016 | A | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, work in progtress,, ok so far,, needs more blocking at panel edges,, ok to cover exterior when done
|
BLD-Footing | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PASS |
Tony Young
|
|
|
Larry-pour time 2:00 Phone #: ###-####,, footing and foundation ok now
|
BLD-Foundation | 10/10/2016 | 10/11/2016 | 10/11/2016 | A | FAIL |
Tony Young
|
|
|
Larry-pour time 2:00 Phone #: ###-####,, c/n posted,, need soils approval
|
BLD-Footing | 10/5/2016 | 10/6/2016 | 10/6/2016 | A | FAIL |
Phil Shearer
|
|
|
Larry// pour time 1030 Phone #: ###-####. No subgrade inspection or footing inspection before placing concrete
|