Permit Information
Permit NumberBLD16-03774
StatusFinaled
Name BIG D BUILDERS
Site Address 2403 S LIBERTY RD
Project NameBA Fischer Office & Warehouse
Customer Number 
ePlanReviewYes
Description
(BA FISCHER) ""MODIFICATION TO THE GAURD ON THE INTERIOR STAIRS"" Permit for the construction of a new 17,720 sq. ft. two story warehouse/office building with work to include the construction of a premanufactured steel structure with a concrete foundation and concrete slab floor. This is a fully fire sprinklered building for height and the S-1 occupancy. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/7/20176/8/20176/8/2017PPASS
DetailsBrandon Shaw
Inspection requested via web by Ferd Smith
DOC - Permit Finaled6/8/20176/8/20176/8/2017PPASS
DetailsBrandon Shaw
DOC - Permit Finaled6/8/20176/8/20176/8/2017PPASS
DetailsBrandon Shaw
FIRE-Final Inspection6/7/20176/8/20176/8/2017APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection6/6/20176/7/20176/7/2017PFAIL
DetailsTroy Cobbley
Need the project related fire alarm and fire sprinkler pemits addressed. Need single action hardware on the north office door, need correct fire extinguishers in warehouse, need signage on the Electrical Room/Fire Alarm Panel door.
BLD-Conference5/8/20175/8/20175/8/2017PDONE
DetailsMike Jordan
Responded to a complaint from the land owner to the north of the project. Noted pitrun that was on land to the north. Spoke with contractor, they will remove all pitrun and northern parcell.
BLD-Framing/Rough-in3/28/20173/29/20173/29/2017ACANC
DetailsMike Jordan
Framing inspection Phone #: ###-#### Inspection requested via web by Ferd Smith
BLD-Energy code compliance3/29/20173/29/20173/29/2017PPASS
DetailsMike Jordan
Framing inspection Phone #: ###-#### Inspection requested via web by Ferd Smith
BLD-Framing/Rough-in3/29/20173/29/20173/29/2017PPART
DetailsMike Jordan
Interior steel stud framed walls and hardlid for office area. Contractor to have architect resubmit deatails for guards on stairs. Owner has deleted the wall and stairs guards are now non code compliant.
BLD-Energy code compliance2/23/20172/24/20172/24/2017PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Ferd Smith
BLD-Energy code compliance2/6/20172/9/20172/9/2017PPASS
DetailsMike Jordan
Inspect visqueen and foundation insulation in bay 8 ; 9. Phone #: ###-#### Inspection requested via web by Ferd Smith. rigid insualtion under slab ok.
BLD-Energy code compliance11/28/201611/29/201611/29/2016PPART
DetailsMike Jordan
Ferd Phone #: ###-####. Rigid insulation aginst stemwall interior side. Ok to backfill. Wiil provide the remainder of rigid insulation horizontally under slab on grade.