BLD-Final | 10/20/2017 | 10/20/2017 | 10/20/2017 | P | PASS |
Jim Sly
|
|
|
Ken Phone #: ###-####
|
DOC - Permit Finaled | 10/20/2017 | 10/20/2017 | 10/20/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 10/16/2017 | 10/17/2017 | 10/17/2017 | A | NR |
Jim Sly
|
|
|
Ken Phone #: ###-#### Need Zoning and Plumbing final.
|
FIRE-Final Inspection | 10/10/2017 | 10/11/2017 | 10/11/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Ken was going to install the address on both sides of the building prior to a building sign off. I discussed providing the small documents to the building inspector Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/9/2017 | 10/10/2017 | 10/10/2017 | A | FAIL |
Troy Cobbley
|
|
|
Need the city approved plans, need building address, need stickers at doors, need tags on fire extinguishers. Emergency lights and exit signs tested ok.
Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/6/2017 | 10/9/2017 | 10/9/2017 | P | FAIL |
Troy Cobbley
|
|
|
Left message on voice mail that I would be there in 20 or 30 minutes. Arrive at job site but had no contact or access. I left another voice message to re-schedule.
Ken-please call 30 minutes prior to meet for access Phone #: ###-####
|
BLD-Wall cover | 8/14/2017 | 8/15/2017 | 8/16/2017 | P | PASS |
Jim Sly
|
|
|
dry wall- ken Phone #: ###-#### 1hr wall....OK
|
BLD-Energy code compliance | 8/3/2017 | 8/4/2017 | 8/4/2017 | P | PASS |
Jim Sly
|
|
|
Ken Phone #: ###-####
|
BLD-Framing/Rough-in | 7/28/2017 | 7/31/2017 | 8/1/2017 | P | PASS |
Jim Sly
|
|
|
Ken Phone #: ###-####
|
BLD-Conference | 7/10/2017 | 7/11/2017 | 7/11/2017 | A | DONE |
Jim Sly
|
|
|
Call ahead for access - Ken Phone #: ###-####
|
BLD-Other | 6/22/2017 | 6/23/2017 | 6/23/2017 | A | PASS |
Jim Sly
|
|
|
fire tape sheetrock (between 10-noon) // Sharm Phone #: ###-#### Exterior side of East wall.....5/8 rock installation.....OK.
|
BLD-Other | 6/7/2017 | 6/7/2017 | 6/7/2017 | P | DONE |
Jim Sly
|
|
|
Sean Phone #: ###-#### Perimeter foundation insulation OK
|
BLD-Footing | 5/19/2017 | 5/22/2017 | 5/22/2017 | A | PASS |
Jim Sly
|
|
|
prefer around 10am // Shawn Nelson Phone #: ###-#### OK pending Geotech special insp, tests and approvals.
|
BLD-Foundation | 5/16/2017 | 5/17/2017 | 5/17/2017 | P | DONE |
Jim Sly
|
|
|
Rebar // Sean Phone #: ###-#### Pre-Construction Conference. GeoTech will be doing all special inspections.
|