BLD-Final | 4/3/2018 | 4/4/2018 | 4/4/2018 | A | PASS |
Jim Sly
|
|
|
Perm C of O Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Final | 4/2/2018 | 4/2/2018 | 4/3/2018 | P | PART |
Jim Sly
|
|
|
Late afternoon if possible Phone #: ###-#### Inspection requested via web by Chris Palmer OK for Temp. Occ. OK for Perm. Occ. when Plumbing finals.
|
BLD-Final | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
BLD-Final | 3/16/2018 | 3/16/2018 | 3/16/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled, Need city approved plans and small documents. No testing was performed.
Please coordinate with sprinkler and alarm. Thanks Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Conference | 3/8/2018 | 3/9/2018 | 3/9/2018 | A | DONE |
Jim Sly
|
|
|
Pre-final/CofO Conference Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Ceiling Grid Inspection | 1/11/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Jim Sly
|
|
|
Admin Bldg. Please coordinate with electrical inspection scheduled for pm. Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer Interior sound batts
|
BLD-Energy code compliance | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PASS |
Jim Sly
|
|
|
Exterior walls foam insulation in the Admin Bldg. Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PASS |
Jim Sly
|
|
|
Dave Phone #: ###-####
|
BLD-Other | 6/28/2017 | 6/29/2017 | 6/29/2017 | P | PART |
Jim Sly
|
|
|
insp for reinforcement for slab on grade for admin classroom building // Justin Rueb Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 6/22/2017 | 6/26/2017 | 6/26/2017 | P | PART |
Mike Jordan
|
|
|
reinforcing for slab on grade // Dave Perkins Phone #: ###-####. Ok, pending special inspection.
|
BLD-Wall Bracing | 6/5/2017 | 6/6/2017 | 6/7/2017 | P | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### Should be Concrete.......MTI on site.
|