BLD-Final | 4/3/2018 | 4/4/2018 | 4/4/2018 | A | PASS |
Jim Sly
|
|
|
Perm C of O Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Final | 4/2/2018 | 4/2/2018 | 4/3/2018 | P | PART |
Jim Sly
|
|
|
Late afternoon if possible Phone #: ###-#### Inspection requested via web by Chris Palmer OK for Temp. Occ. OK for Perm Occ when Plumbing finals.
|
BLD-Final | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
FIRE-Final Inspection | 3/26/2018 | 3/27/2018 | 3/27/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled. All other life safety items appear ok. The address is temp. Also per the assistant chief the fire hydrant bollards and the gate access will be handled by the fire dept.
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Ceiling Grid Inspection | 1/23/2018 | 1/24/2018 | 1/24/2018 | P | PASS |
Jim Sly
|
|
|
Grid at the Training Safety Bldg. Please coordinate with Mechanical. Thanks! Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Jim Sly
|
|
|
Upper walls and overhead door walls in the Apparatus Bay at the Training/Safety Bldg Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 12/14/2017 | 12/15/2017 | 12/15/2017 | P | PASS |
Jim Sly
|
|
|
Wall framing in the apparatus bay in the Training Bldg. Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 11/29/2017 | 11/30/2017 | 11/30/2017 | A | PASS |
Jim Sly
|
|
|
Batt insulation in the Training/Safety Building Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PASS |
Jim Sly
|
|
|
Exterior wall foam insulation inspection in the Safety/Training Building. Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 11/13/2017 | 11/14/2017 | 11/14/2017 | A | PASS |
Jim Sly
|
|
|
Fire Training and Safety Building framing inspection Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Concrete | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PART |
Jim Sly
|
|
|
before 9am please rebar- david Phone #: ###-#### OK pending MTI special inspections, tests and approvals.
|
BLD-Other | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | PART |
Jim Sly
|
|
|
grouting at 9:30 for CMU reinforcement - Dave Phone #: ###-#### OK pending MTI special inspection tests and approval.
|
BLD-Footing | 6/30/2017 | 7/5/2017 | 7/5/2017 | A | PART |
Jim Sly
|
|
|
Requesting 9am- Rebar for stem wall -Justin Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 6/22/2017 | 6/23/2017 | 6/23/2017 | P | PART |
Jim Sly
|
|
|
Dave Perkins Phone #: ###-#### Footing for Safety Training Bldg OK pending MTI special inspections, tests and approvals.
|