Permit Information
Permit NumberBLD16-04079
StatusFinaled
Name ESI
Site Address 12142 W JOPLIN RD
Project NameBFD - Training/Safety
Customer Number 
ePlanReviewYes
Description
(BOISE FIRE DEPARTMENT – TRAINING & SAFETY BUILDING)(***GREEN CONSTRUCTION CODE USED - PRIORITY REVIEW*** ) To meet 2012 International Green Construction Code as adopted. To construct a 9,813 sq. ft. one story commercial business building and related site improvements. Scope of work includes: construction of a slab on grade concrete foundation, CMU exterior envelope walls, open web steel roof joist, steel roof decking, electrical, mechanical and plumbing work and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. Sprinklers used for area increase. This building will be fully Fire Sprinklered with an approved Fire Alarm system. System shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. Note: Special Inspections Required see form 310. Note: This building requires a Preoccupancy Commissioning Report, this report shall be submitted and accepted by the Building Official prior to issuance of the Certificate of Occupancy. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/3/20184/4/20184/4/2018APASS
DetailsJim Sly
Perm C of O Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Final4/2/20184/2/20184/3/2018PPART
DetailsJim Sly
Late afternoon if possible Phone #: ###-#### Inspection requested via web by Chris Palmer
OK for Temp. Occ. OK for Perm Occ when Plumbing finals.
BLD-Final3/29/20183/29/20183/29/2018PCANC
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
FIRE-Final Inspection3/26/20183/27/20183/27/2018APASS
DetailsTroy Cobbley
life safety passed

Phone #: ###-#### Inspection requested via web by Chris Palmer
FIRE-Final Inspection3/22/20183/23/20183/23/2018AFAIL
DetailsTroy Cobbley
Need the project related fire alarm and fire sprinkler permits finaled. All other life safety items appear ok. The address is temp. Also per the assistant chief the fire hydrant bollards and the gate access will be handled by the fire dept.


Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Ceiling Grid Inspection1/23/20181/24/20181/24/2018PPASS
DetailsJim Sly
Grid at the Training Safety Bldg. Please coordinate with Mechanical.
Thanks! Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Energy code compliance1/3/20181/4/20181/4/2018APASS
DetailsJim Sly
Upper walls and overhead door walls in the Apparatus Bay at the Training/Safety Bldg Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in12/14/201712/15/201712/15/2017PPASS
DetailsJim Sly
Wall framing in the apparatus bay in the Training Bldg. Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Energy code compliance11/29/201711/30/201711/30/2017APASS
DetailsJim Sly
Batt insulation in the Training/Safety Building Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Energy code compliance11/20/201711/21/201711/21/2017APASS
DetailsJim Sly
Exterior wall foam insulation inspection in the Safety/Training Building. Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in11/13/201711/14/201711/14/2017APASS
DetailsJim Sly
Fire Training and Safety Building framing inspection Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Concrete8/16/20178/17/20178/17/2017APART
DetailsJim Sly
before 9am please rebar- david Phone #: ###-####
OK pending MTI special inspections, tests and approvals.
BLD-Other8/2/20178/3/20178/3/2017APART
DetailsJim Sly
grouting at 9:30 for CMU reinforcement - Dave Phone #: ###-####
OK pending MTI special inspection tests and approval.
BLD-Footing6/30/20177/5/20177/5/2017APART
DetailsJim Sly
Requesting 9am- Rebar for stem wall -Justin Phone #: ###-####
OK pending MTI special inspection, tests and approvals.
BLD-Footing6/22/20176/23/20176/23/2017PPART
DetailsJim Sly
Dave Perkins Phone #: ###-####
Footing for Safety Training Bldg OK pending MTI special inspections, tests and approvals.