BLD-Final | 4/2/2018 | 4/2/2018 | 4/3/2018 | P | PASS |
Jim Sly
|
|
|
Late afternoon if possible Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Final | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
|
FIRE-Final Inspection | 3/28/2018 | 3/29/2018 | 3/29/2018 | P | PASS |
Troy Cobbley
|
|
|
As per activity notes, no inspection required, hydrants and fire dept access under the associated Grading permit
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Final | 3/27/2018 | 3/28/2018 | 3/29/2018 | A | CANC |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIRE-Final Inspection | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need the Grading permit finaled
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | PASS |
Jim Sly
|
|
|
Dave-roof framing Phone #: ###-####
|
BLD-Foundation | 8/25/2017 | 8/25/2017 | 8/28/2017 | P | CANC |
Jim Sly
|
|
|
|
BLD-Foundation | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | CANC |
Brandon Shaw
|
|
|
Rebar // Dave Phone #: ###-####
|
BLD-Other | 8/16/2017 | 8/17/2017 | 8/17/2017 | P | PART |
Jim Sly
|
|
|
for deck david Phone #: ###-#### OK pending MTI approvals.
|
BLD-Foundation | 5/22/2017 | 5/23/2017 | 5/23/2017 | P | PART |
Jim Sly
|
|
|
Rebar // Dave Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|