Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD16-04308
StatusFinaled
Name SUMMIT DEVELOPMENT INC
Site Address 7719 W PREECE DR
Project NameMarena Apartments
Customer NumberBLD16-04309 THRU 04316, 17-01176
ePlanReviewYes
Description
(MARENA APARTMENTS) (10 PERMITS TOTAL FILED UNDER BLD16-04308 IN EPLANREVIEW) For the construction of a 8,555 sq. ft. six plex including the attached garages and the covered entries with 6, two story units and work to include general site work and construction of the new building per the approved plans. This building is fully fire sprinklered for R-2 occupancy. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/11/20184/11/20184/11/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by David Scaggs
BLD-Final2/14/20182/14/20182/14/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by David Scaggs. Temp occ. Will be for perm occ. once zoning signs perm.
BLD-Final2/5/20182/6/20182/6/2018PCANC
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by David Scaggs
BLD-Conference2/6/20182/6/20182/6/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by David Scaggs
BLD-Final2/2/20182/2/20182/2/2018PCANC
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by David Scaggs
BLD-Final2/1/20182/2/20182/2/2018APART
DetailsMike Jordan
Please accommodate a 10:30 inspection. Fire final is scheduled for 10 o''clock. Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp occ. Needs to provide 5/8 type x rock at HVac ductwork in garage and repair 1 hr. walls.
FIRE-Final Inspection2/1/20182/2/20182/2/2018APASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Final Inspection1/31/20182/1/20182/1/2018AFAIL
DetailsTroy Cobbley
Need smoke alarms to be located atleast 3' from fan blades and re-tested, need fees paid and inspection called in for the project related fire alarm permit. Need paint removed from the FDC.
BLD-Final1/31/20182/1/20182/1/2018PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by David Scaggs. Needs plumbing, life safety and fire finals
BLD-Framing/Rough-in11/22/201711/22/201711/22/2017PPASS
DetailsMike Jordan
BLD-Energy code compliance11/22/201711/22/201711/22/2017PPASS
DetailsMike Jordan
BLD-Framing/Rough-in11/15/201711/16/201711/16/2017PFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by david scaggs. Repair all holes, f
complete fire caulking and complete install of sheetrock on fire partition in attics. Provide fix from joist manufacturer for all cut top chords on floor joist and repair. Install bracing on top chords of trusses at over builds were roof sheathing has been left off.
BLD-Framing/Rough-in11/9/201711/13/201711/12/2017ACANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by david scaggs Inspection cancelled from web by: david scaggs
BLD-Wall Bracing9/20/20179/20/20179/20/2017APASS
DetailsMike Jordan
Exterior Shear Inspection requested via web by Marty Short
BLD-Concrete7/20/20177/20/20177/20/2017PPASS
DetailsMike Jordan
Garage int footings Inspection requested via web by Marty Short
BLD-Concrete7/17/20177/18/20177/18/2017APASS
DetailsMike Jordan
Int footings. Concrete is scheduled for 8am Inspection requested via web by Marty Short
BLD-Energy code compliance7/10/20177/11/20177/11/2017APASS
DetailsMike Jordan
Rigid insulation Inspection requested via web by Marty Short