Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD16-04480
StatusIssued
Name HEADWATERS CONSTRUCTION COMPANY
Site Address 348 S 13TH ST
Project NameHilton Garden Inn
Customer NumberBLD17-00583, GRD17-00003
ePlanReviewYes
Description
(HILTON GARDEN INN - BOISE) Foundation, site grading and utilities to include underground plumbing (approved under BLD17-00583). No vertical construction is allowed. Work is allowed to be done at the owners risk any items found to be not in compliance upon approval of the plans shall be corrected prior to any further work being completed.. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/24/20189/24/20189/24/2018PPASS
DetailsDave Hannah
David Banks ###-####
BLD-Final10/17/201710/19/201710/20/2017PCANC
DetailsDave Hannah
Chris-this is to close the foundation Phone #: ###-####
BLD-Aging Inspection10/12/201710/12/201710/16/2017 PEND
DetailsDave Hannah
BLD-Aging Inspection10/11/201710/11/201710/16/2017 PEND
DetailsDave Hannah
BLD-Conference6/29/20176/30/20176/29/2017ACANC
DetailsDave Hannah
Building fire rating consultation. Phone #: ###-#### >> Inspection requested via web by Nicholas Miller Inspection cancelled from web by: Nicholas Miller
BLD-Concrete5/23/20175/25/20175/30/2017APASS
DetailsDave Hannah
7 am slab pour. 65 yards of concrete. MTI will be present. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing5/23/20175/23/20175/24/2017PPEND
DetailsDave Hannah
Footings at 2pm. MTI will be present as always. Phone #: ###-#### Inspection requested via web by Nicholas Miller ok after spec insection sign off
BLD-Concrete4/20/20174/21/20174/21/2017APASS
DetailsDave Hannah
We will be pouring one third of our building slab starting at 8 am. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing4/14/20174/17/20174/18/2017PPASS
DetailsDave Hannah
The pour is scheduled for 1PM. MTI will also be present for a rebar inspection. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Conference4/12/20174/13/20174/13/2017ADONE
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Nicholas Miller. question regarding the sprinkler system being energized prior to vertical construction. Refered to fire.
BLD-Foundation3/31/20173/31/20174/3/2017PPASS
DetailsDave Hannah
The pour is scheduled for 1 pm. MTI will be present to inspect the rebar and oversee the pour. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Foundation3/29/20173/30/20173/30/2017ACANC
DetailsDave Hannah
The pour is scheduled for 9 am. MTI will be present for a rebar inspection. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing3/27/20173/28/20173/29/2017PPASS
DetailsDave Hannah
The pour is scheduled for 2 pm. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Foundation3/27/20173/28/20173/29/2017PPASS
DetailsDave Hannah
The pour is scheduled for 2 pm. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing3/21/20173/23/20173/23/2017APASS
DetailsDave Hannah
The pour is scheduled for 11. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing3/21/20173/22/20173/23/2017APASS
DetailsDave Hannah
The pour is scheduled for 11. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing3/15/20173/16/20173/20/2017APASS
DetailsDave Hannah
The pour is scheduled for noon. We plan on pouring footings and foundation walls on the east and west ends of the building. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Foundation3/15/20173/16/20173/20/2017APASS
DetailsDave Hannah
The pour is scheduled for noon. We plan on pouring footings and foundation walls on the east and west ends of the building. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Foundation3/8/20173/9/20173/10/2017APASS
DetailsDave Hannah
The concrete pour is scheduled for noon tomorrow. We plan on pouring footings and foundation. I will request an inspection for both. Thank you. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing3/8/20173/9/20173/10/2017APASS
DetailsDave Hannah
The concrete pour is scheduled for noon tomorrow. We plan on pouring footings and foundation. I will request an inspection for both. Thank you. Phone #: ###-#### Inspection requested via web by Nicholas Miller
BLD-Footing2/28/20173/1/20173/1/2017APEND
DetailsDave Hannah
Pour at 11 // Nick Phone #: ###-#### ok after spec inspection sign off
BLD-Foundation2/22/20172/23/20172/23/2017APASS
DetailsDave Hannah
Pouring at 10 - Chris-rebar Phone #: ###-####
BLD-Foundation2/14/20172/15/20172/15/2017APEND
DetailsDave Hannah
Chris Phone #: ###-####