BLD-Final | 9/12/2017 | 9/13/2017 | 9/13/2017 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 9/13/2017 | 9/13/2017 | 9/13/2017 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | NR |
Tony Young
|
|
|
Call for garage code - Dan Phone #: ###-####,, conf only
|
BLD-Foundation | 7/17/2017 | 7/18/2017 | 7/18/2017 | P | DONE |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 7/14/2017 | 7/17/2017 | 7/17/2017 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, porch foundation,, poured
|
BLD-Footing | 7/13/2017 | 7/14/2017 | 7/14/2017 | P | NR |
Tony Young
|
|
|
Jerry Phone #: ###-####
|
BLD-Footing | 7/12/2017 | 7/13/2017 | 7/13/2017 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 7/11/2017 | 7/12/2017 | 7/12/2017 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Energy code compliance | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Tony Young
|
|
|
Mid pm please Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Energy code compliance | 5/30/2017 | 5/31/2017 | 6/1/2017 | P | NR |
Tony Young
|
|
|
Mid pm please Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall cover | 5/30/2017 | 5/31/2017 | 5/31/2017 | P | PART |
Tony Young
|
|
|
Mid pm please Dan Phone #: ###-#### Inspection requested via web by Daniel Appel// work in progress,, ok
|
BLD-Framing/Rough-in | 5/25/2017 | 5/25/2017 | 5/25/2017 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-####
|
BLD-Framing/Rough-in | 5/24/2017 | 5/25/2017 | 5/25/2017 | A | DEFR |
Tony Young
|
|
|
Dan Phone #: ###-####, needs mech 1st
|
BLD-Wall Bracing | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PART |
Jim Sly
|
|
|
Shear // Dan Phone #: ###-#### Exterior Shear Nailing Only....OK. Check Shear panel N.of Garage doors. Required HD9B's (2) attached to 3 studs. (not installed yet). panel nailing 8d at 4/12.
|
BLD-Energy code compliance | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####. Rigid insulation on stemwall under slab on grade.
|
BLD-Foundation | 3/27/2017 | 3/28/2017 | 3/28/2017 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress
|
BLD-Footing | 3/24/2017 | 3/27/2017 | 3/27/2017 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 3/23/2017 | 3/24/2017 | 3/24/2017 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 3/22/2017 | 3/23/2017 | 3/23/2017 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 3/21/2017 | 3/22/2017 | 3/22/2017 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### no one on site on forms ect
|