Permit Information
Permit NumberBLD17-00058
StatusFinaled
Name KIER CONSTRUCTION CORPORATION
Site Address 7353 W VICTORY RD
Project NameMaverik #565
Customer Number 
ePlanReviewYes
Description
(MAVERIK #565) //Plan modification to structural canopy framing, structural side entry footing, structural heavy timber, storefront area overhead beams, structural overhead beam at beer cooler, structural connection to HSS, structural joist bearing on beam, sink support, select interior and exterior finishes, men’s and women’s accessible restroom layout, kitchen equipment layout, relocation and added floor sinks, floor drains and sinks at kitchen area, millwork, exterior air barrier type, interior and exterior lighting, plumbing, mechanical, electrical, exterior work and site work. 11-28-2017 JG// Permit to construct a new 5,524 sq., ft. building one story metal stud framed convenience store, two fuel canopies (auto canopy is 207’ x 26’ and RV canopy 64’ x 26’), three trellis’s and related site improvements. Scope of work includes: construction of a slab on grade concrete, foundation, construction of steel stud framed exterior envelope walls, roof construction, construction of interior non-bearing walls to create a retail area, an office, an electrical room, men’s and women’s accessible restrooms, kitchen area, and storage areas, (4) coolers, new windows and doors, new electrical, new mechanical, new plumbing, site work, and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. The building is not fire sprinklered. Note: Special Inspections Required see form 310. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/3/20184/3/20184/3/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves. All issues have been resolved. Ok for perm occ.
BLD-Final3/20/20183/21/20183/21/2018APART
DetailsMike Jordan
late am please Phone #: ###-#### Inspection requested via web by Roger Graves. Ok for temp occ. Needs smoke and flame spread values for foam plastics on walk in cooler and can not verify tempered glazing in door to office.
BLD-Final3/19/20183/19/20183/19/2018PNR
DetailsMike Jordan
Needs zonimg and public works finals.
BLD-Final3/16/20183/19/20183/19/2018ACANC
DetailsMike Jordan
Requesting a late am inspection Phone #: ###-#### Inspection requested via web by Roger Graves
FIRE-Final Inspection3/13/20183/15/20183/15/2018PPASS
DetailsTroy Cobbley
Life safety passed.

Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Final3/13/20183/15/20183/13/2018PCANC
DetailsMike Jordan
I will have an electrician and HVAC rep available in the afternoon for the inspection. A scheduled time of inspection would be appreciated. Phone #: ###-#### >> Inspection requested via web by Roger Graves Inspection cancelled from web by: Roger Graves
FIRE-Final Inspection3/12/20183/13/20183/13/2018AFAIL
DetailsTroy Cobbley
Provide sign off from Boise FIre Dept, repair exit sign at west end of corridor, repair exit discharge light at west main exit, provide testing of communication, emergency stops and duct smoke detectors, remove dead bolt on the beer cooler, provide address numbers facing Cole Rd.

Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Ceiling Grid Inspection2/13/20182/14/20182/14/2018APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Ceiling Grid Inspection2/12/20182/13/20182/13/2018PFAIL
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Graves not per plan with seicmic pods and wires
BLD-Energy code compliance1/11/20181/12/20181/12/2018PPASS
DetailsMike Jordan
Early afternoon inspection please Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Framing/Rough-in1/11/20181/12/20181/12/2018PPASS
DetailsMike Jordan
Early afternoon inspection please Phone #: ###-#### Inspection requested via web by Roger Graves. All framing issues have been resolved.
BLD-Framing/Rough-in1/9/20181/10/20181/10/2018APART
DetailsMike Jordan
Late am inspection please Phone #: ###-#### Inspection requested via web by Roger Graves. Add additional steel stud under joist for full bearing. 5/8 through bolts on side entry need to penetrate through osb, and stud back and connected with 1/4 inch washers and nut. ok to insulate. Also inspected in progress work on heavy timber connections on ground.
BLD-Framing/Rough-in12/12/201712/13/201712/13/2017ACANC
DetailsMike Jordan
Roger Phone #: ###-####
BLD-Framing/Rough-in12/13/201712/13/201712/13/2017PPART
DetailsMike Jordan
Interior walls only. No cover on exterior or storefront. Waiting for structural reveiw.
BLD-Framing/Rough-in12/12/201712/12/201712/12/2017PFAIL
DetailsMike Jordan
Needs to pull electrical permit from boise city. Also noted sheet rock installed and coolers, no cover or energy code inspctions have been done at this time.
BLD-Framing/Rough-in12/8/201712/11/201712/11/2017PDEFR
DetailsJim Storey
Roger Phone #: ###-#### out of time rolled to mike am
BLD-Framing/Rough-in12/5/201712/6/201712/6/2017PCANC
DetailsMike Jordan
Roger Phone #: ###-####
BLD-Wall Bracing12/6/201712/6/201712/6/2017PPASS
DetailsMike Jordan
Roger Phone #: ###-####. The south exteror wall below the low roof has been corrected.
BLD-Framing/Rough-in12/1/201712/5/201712/5/2017ACANC
DetailsMike Jordan
Roger Phone #: ###-####
BLD-Wall Bracing12/5/201712/5/201712/5/2017APART
DetailsMike Jordan
Roger Phone #: ###-####. Exterior walls. South exterior wall below low roof not completed.
BLD-Footing10/30/201710/31/201710/31/2017APASS
DetailsMike Jordan
Requesting canopy footing inspection. Concrete is scheduled to pour at 2 PM Phone #: ###-#### Inspection requested via web by Roger Graves. Canopy footings for North canopy ok.
BLD-Footing10/24/201710/25/201710/25/2017APART
DetailsBrandon Shaw
Diesel fuel canopy
BLD-Foundation10/18/201710/19/201710/19/2017PPASS
DetailsMike Jordan
Requesting an afternoon inspection. Concrete pour is set up for Friday morning Phone #: ###-#### Inspection requested via web by Roger Graves. Perimeter stemwalls. Will have special ionspection.
BLD-Footing10/13/201710/16/201710/16/2017APASS
DetailsMike Jordan
Requesting 9:00am inspection. Have mud scheduled for 10 am. Will have city stamped approved plans on site. Phone #: ###-#### Inspection requested via web by Roger Graves. Perimeter footings ok.
BLD-Footing10/12/201710/13/201710/13/2017PNR
DetailsMike Jordan
Building footings. QAA set for 12:00. Mud set for delivery at 2:00 PM. Please try to accommodate a noon inspection. Phone #: ###-#### x801 Inspection requested via web by Roger Graves. No city approved plans on site. Will reschedule.