Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberBLD17-00090
StatusIssued
Name ST LUKES HEALTH SYSTEM LTD
Site Address 305 E JEFFERSON ST
Project NameSt. Luke's Children's Pavilion
Customer Number 
ePlanReviewYes
Description
(ST. LUKE'S CHILDRENS PAVILION)(STRUCTURAL STEEL AND CONCRETE ONLY) This is the Steel & Concrete Package of the Children's Pavilion. This package will include any structural, electrical, plumbing work dealing with the construction of any structural steel and concrete. All building code items for TI will be reviewed under future submittals. Special Inspections Required pre form #310. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection12/14/201712/14/201712/19/2017 PEND
DetailsDave Hannah
BLD-Aging Inspection12/13/201712/13/201712/19/2017 PEND
DetailsDave Hannah
BLD-Concrete9/14/20179/15/20179/15/2017PPEND
DetailsDave Hannah
Rebar inspection request for the suspended slab on deck. Placement is from grid 7.5 to 11 and from grid A to E. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski ok after spec inspection sign off
BLD-Foundation8/15/20178/15/20178/18/2017PPEND
DetailsDave Hannah
Final reinforcement sign off for the perimeter walls at LL3. These are along grids 1-11 and A-E. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
BLD-Concrete8/1/20178/1/20178/1/2017ADONE
DetailsDave Hannah
Rebar inspection of structural mat slab. Grids 5 to 11 from A to E. Phone #: ###-#### Inspection requested via web by Dan Koski
BLD-Foundation7/28/20177/28/20178/1/2017PPASS
DetailsDave Hannah
Rebar inspection of structural mat slab. Grids 5 to 11 from A to E. Phone #: ###-#### Inspection requested via web by Dan Koski
BLD-Foundation7/18/20177/18/20177/18/2017APART
DetailsBrandon Shaw
5.5 to 11, between A & E
BLD-Foundation6/26/20176/29/20177/12/2017ADONE
DetailsDave Hannah
Inspection of LL3 foundation reinforcement complete - 1,900cy concrete placement scheduled for 0100hr start on 7/1 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Foundation7/11/20177/11/20177/12/2017PPEND
DetailsDave Hannah
Rebar // Dan Phone #: ###-####
BLD-Foundation6/21/20176/22/20176/23/2017PPEND
DetailsDave Hannah
Bottom mat reinforcement - mat slab @ level LL3 Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Foundation6/14/20176/15/20176/16/2017PPASS
DetailsDave Hannah
Elevator pit reinforcement Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Footing6/1/20176/2/20176/5/2017PPASS
DetailsDave Hannah
Concrete reinforcement at tower crane foundation Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD-Conference5/23/20175/30/20175/30/2017APASS
DetailsDave Hannah
Meeting requested with Dave Hannah to discuss start of construction activities specific to this permit. Phone #: ###-#### Inspection requested via web by Jamal Nelson