BLD-Aging Inspection | 12/14/2017 | 12/14/2017 | 12/19/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 12/13/2017 | 12/13/2017 | 12/19/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Concrete | 9/14/2017 | 9/15/2017 | 9/15/2017 | P | PEND |
Dave Hannah
|
|
|
Rebar inspection request for the suspended slab on deck. Placement is from grid 7.5 to 11 and from grid A to E. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski ok after spec inspection sign off
|
BLD-Foundation | 8/15/2017 | 8/15/2017 | 8/18/2017 | P | PEND |
Dave Hannah
|
|
|
Final reinforcement sign off for the perimeter walls at LL3. These are along grids 1-11 and A-E. Please call Dan with any questions. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Concrete | 8/1/2017 | 8/1/2017 | 8/1/2017 | A | DONE |
Dave Hannah
|
|
|
Rebar inspection of structural mat slab. Grids 5 to 11 from A to E. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Foundation | 7/28/2017 | 7/28/2017 | 8/1/2017 | P | PASS |
Dave Hannah
|
|
|
Rebar inspection of structural mat slab. Grids 5 to 11 from A to E. Phone #: ###-#### Inspection requested via web by Dan Koski
|
BLD-Foundation | 7/18/2017 | 7/18/2017 | 7/18/2017 | A | PART |
Brandon Shaw
|
|
|
5.5 to 11, between A & E
|
BLD-Foundation | 6/26/2017 | 6/29/2017 | 7/12/2017 | A | DONE |
Dave Hannah
|
|
|
Inspection of LL3 foundation reinforcement complete - 1,900cy concrete placement scheduled for 0100hr start on 7/1 Phone #: ###-#### Inspection requested via web by Jamal Nelson
|
BLD-Foundation | 7/11/2017 | 7/11/2017 | 7/12/2017 | P | PEND |
Dave Hannah
|
|
|
Rebar // Dan Phone #: ###-####
|
BLD-Foundation | 6/21/2017 | 6/22/2017 | 6/23/2017 | P | PEND |
Dave Hannah
|
|
|
Bottom mat reinforcement - mat slab @ level LL3 Phone #: ###-#### Inspection requested via web by Jamal Nelson
|
BLD-Foundation | 6/14/2017 | 6/15/2017 | 6/16/2017 | P | PASS |
Dave Hannah
|
|
|
Elevator pit reinforcement Phone #: ###-#### Inspection requested via web by Jamal Nelson
|
BLD-Footing | 6/1/2017 | 6/2/2017 | 6/5/2017 | P | PASS |
Dave Hannah
|
|
|
Concrete reinforcement at tower crane foundation Phone #: ###-#### Inspection requested via web by Jamal Nelson
|
BLD-Conference | 5/23/2017 | 5/30/2017 | 5/30/2017 | A | PASS |
Dave Hannah
|
|
|
Meeting requested with Dave Hannah to discuss start of construction activities specific to this permit. Phone #: ###-#### Inspection requested via web by Jamal Nelson
|