Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD17-00222
StatusFinaled
Name PANORAMA CONSTRUCTION
Site Address 9931 W CABLE CAR ST Unit: 110
Project NameGrowlers
Customer Number 
ePlanReviewYes
Description
(GROWLERS – RESTAURANT – EAST END OF THE BUILDING) The fire sprinkler system is used for occupancy, for building area increase, and for fire flow. To construct interior improvements for a new 3,500 square foot restaurant and bar. Work is to include a concrete slab on grade, interior nonbearing walls, two restrooms accessible to the disabled, suspended acoustical ceilings, gypsum board ceilings, kitchen equipment, a Type I grease hood and duct system, wall insulation, attic insulation, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. Separate fire sprinkler permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/2/20176/5/20176/5/2017PPASS
DetailsMike Jordan
Jeff Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection6/2/20176/5/20176/5/2017APASS
DetailsTroy Cobbley
life safety passed
BLD-Final5/23/20175/23/20175/23/2017PPART
DetailsMike Jordan
jeff Phone #: ###-####. All isues resolved. ok for temp occ. will be ok for perm occ. once fire/life/safety signs perm.
BLD-Final5/19/20175/22/20175/22/2017APART
DetailsMike Jordan
Jeff Phone #: ###-####. Lower bathroom lavs to 34 inch max height. Provide ADA POS. ok for temp occ. when zoning signs off. (Needs two bushes at drive thru, being planted when on site.)
FIRE-Final Inspection5/19/20175/22/20175/22/2017APART
DetailsTroy Cobbley
A temporary occupancy is being given with Scotts permission. I was given a list of trained/fire watch employees and the fire alarm permit has been submitted.

Jeff Phone #: ###-####
FIRE-Final Inspection5/19/20175/19/20175/19/2017PFAIL
DetailsTroy Cobbley
Need the exit discharge lights repaired and a list of employees who are responcible for the fire watch. When they are repaired and list is provided and the fire alarm permit is submitted, per Scott, the project can have a temporary until the interconnect of the kitchen hood suppression system and the two AHU's has been tested.

Jeff Phone #: ###-####
BLD-Energy code compliance4/12/20174/12/20174/12/2017PPASS
DetailsMike Jordan
BLD-Framing/Rough-in4/11/20174/12/20174/12/2017APASS
DetailsMike Jordan
Jeff Phone #: ###-####
BLD-Framing/Rough-in4/11/20174/11/20174/11/2017PPART
DetailsMike Jordan
ok to insulate.
BLD-Framing/Rough-in4/10/20174/10/20174/10/2017PNR
DetailsMike Jordan
Jeff Phone #: ###-####. ok to insulate exterior walls. Provide city set of approved plans.